Table 5.8 Summary
of Investigation on Water Quality Monitoring Exceedance Records in the
Reporting Month
Date |
Monitoring Stations |
Parameters |
Investigation
Summary |
2, 4 and 11 June 2021 |
SYR-IS1 |
DO |
The exceedances are considered
not due to the Contract due to the following reasons: 1) No
pollution discharge from construction activity was observed; 2) DO value
at control station were measured lower than the water quality criteria at
SYR-IS1 (4 June 2021); 3) Water
temperature recorded were relatively higher that that during baseline
monitoring and led to low oxygen solubility in water. |
4, 7 and 9 June 2021 |
SYR-IS1 |
Arsenic |
No pollution discharge from
construction activity was observed. The exceedances are considered due to the
external factors rather than the contract works and non-project related. |
4, 7 and 11 June 2021 |
NTR-IS1 |
DO |
The exceedances are considered
not due to the Contract due to the following reasons: 1) No
pollution discharge from construction activity was observed; 2) DO value
at control station were measured lower than the water quality criteria at NTR-IS1
(4 and 11 June 2021); 3) Water
temperature recorded were relatively higher that that during baseline
monitoring and led to low oxygen solubility in water. |
9 June 2021 |
NTR-IS1 |
Turbidity and SS |
An influx of muddy water from a
tributary (out of Project boundary) to Ma Wat River and then to River Indus
was observed which affect the water quality of River Indus during the
monitoring day. No pollution discharge from construction activity under the
Project was observed. Rainfall was recorded before monitoring which led to
increased surface runoff and hence adverse water quality. The exceedances are
considered due to the external factors rather than the contract works and
non-project related. |
2 and 7 June 2021 |
SHST-IS2 |
DO, turbidity and SS |
No pollution discharge from
construction activity was observed. Rainfall was recorded before monitoring
which led to increased surface runoff and erosion from natural habitat along
the Siu Hang San Tsuen Stream, and also may cause the dispersion of riverbed
sediment to the monitoring station. (2 June 2021). DO value at control station were
measured lower than the water quality criteria at SHST-IS2. The exceeded
results were similar or within the ranges of baseline monitoring results. Water
temperature recorded were relatively higher that that during baseline
monitoring and led to low oxygen solubility in water. The exceedances are
considered due to the external factors rather than the contract works and
non-project related. |
4, 9 and 11 June 2021 |
SHST-IS2 |
DO, turbidity and SS |
Increased surface runoff from
rainfall recorded before and during the water quality monitoring may lead to
erosion from natural habitat along the stream, and also may cause the
dispersion of riverbed sediment to the monitoring station. During monitoring,
muddy surface runoff was observed between gaps of water barrier (under
Contract No. ND/2019/04) near Station SHST-IS2 which was considered as a
source of water pollution. In addition, DO value at control
station were measured lower than the water quality criteria at SHST-IS2.
Water temperature recorded were relatively higher that that during baseline
monitoring and led to low oxygen solubility in water. Remedial works were observed in progress
to clear the sediment trapped by desilting materials, provide concreting for
exposed site area near Siu Hang San Tsuen Stream and provide surface channels
for diverting storm water to wastewater treatment facilities. The following recommendations
on remedial measures were given as below and shall be maintained to avoid
further exceedances: 1) To
regularly clear the slurry and sediment trapped by desilting materials; 2) To
identify and minimise any source of surface runoff within site area near Siu
Hang San Tsuen Stream; 3) To
provide spare pumps for emergency use to pump muddy surface runoff to
wastewater treatment facilities after rainstorm; 4) To
minimise area of exposed soil surface by covering with impervious materials
or clear loosen soil materials to reduce formation of muddy surface runoff; 5) To
frequently check and ensure desilting materials for protection of Siu Hang
San Tsuen Stream are intact and in good condition; 6) To
provide channels, earth bunds or sand bag barriers to direct any muddy water
to silt removal facilities and away from Siu Hang San Tsuen Stream; 7) Regular
supervision and close monitoring on sediment control measures should be
conducted by designated foreman to ensure normal operation; and 8) Proposal
for mitigation measures on sediment control and contingency plan under
Contract No. ND/2019/04 should be submitted to avoid further exceedances. The
effectiveness of the remedial measures implemented should be closely reviewed The effectiveness of remedial
measures implemented by the Contractor would be continuously checked and
reviewed during water quality monitoring and weekly site inspection. |
2, 4, 7, 9 and 11 June 2021 |
MWR-IS3 |
DO,
Turbidity and SS |
Influx of muddy water from a
tributary (out of Project boundary) to Ma Wat River and then to the
monitoring stations was observed which affect the water quality of Ma Wat
River during the monitoring days. No pollution discharge from construction
activity under the Project was observed. DO value at control station were
measured lower than the water quality criteria at MWR-IS3 (2, 4, 9 and 11
June 2021). Water temperature recorded were relatively higher that that
during baseline monitoring and led to low oxygen solubility in water. The
exceedances are considered due to the external factors rather than the
contract works and non-project related. |