Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site Activities
(June 2021) |
ND/2019/01 |
(a)
Site clearance, excavation in Portion 3 (b)
Site Clearance, stockpile of soil, construction of KW01 retaining
wall, sheetpiling and excavation, pipes laying in Portion 5 (c)
Site
Clearance, sheetpiling and excavation, pipes
laying, construction of KW01 retaining wall in Portion 6a (d)
Arsenic
soil treatment works in Portion 6b (e)
Site Clearance, Construction of temporary road for alternative Po
Lau Road, Construction of site accommodation in Area T2 and T3, sheetpiling and excavation, pipes laying, footing of
Noise Barriers in Portion 7 (f)
Construction of Retaining Wall, slope cutting, soil nailing,
slope drainage and maintenance access construction, Excavation for Fresh
Water Service Reservoir, RC construction of Flushing Water Service Reservoir in
Portion 8a (g)
Sheetpiling for jacking
pit in Portion 8b (h)
Sheetpiling and
excavation and pipes laying in Portion 9b (i)
Stockpile of soil and excavation in Portion 9c (j)
Sheetpiling for ELS,
excavation, pipes laying and noise barriers footing in Portion 10a (k)
Sheetpiling and excavation in Portion 10b (l)
Laying of rising mains, construction of MBR in
Portion 11b (m)
Sheetpiling and excavation , Construction of temporary sewage pumping
station in
Portion 14 (n)
Construction of CLC in Portion 16 |
ND/2019/02 |
(a)
Pre-bored
Socketed H-pile (b)
Tree
felling (c)
Hoarding
erection |
ND/2019/03 |
(a)
Underground Utilities Laying in
Portion 1; (b)
Portion 2
to Portion 20 -
Erection
of Permanent Boundary Structure -
Construction of Irrigation Channel -
Geotechnical Works in Long Valley
(Trail Pits) -
Construction of Temporary Road in Long
Valley -
Asbestos Removal in Long Valley -
Demolition of Existing Construction in
Handed
over Area -
Construction of Storage Shed and Type
2 Storage House -
Construction of Bird Hide -
Construction of Outdoor Classroom -
Wetland Creation & Restoration
works |
ND/2019/04 |
(a)
Site clearance (b)
Tree felling (c)
Predrill (d)
Socket H-piling (e)
Bored piling (f)
Excavation (g)
Sheet piling |
ND/2019/05 |
(a)
Bridge Foundation Works -
Ground investigation works at FLN3-DH016, ABH02,
ABH04, ABH10, D39(P). -
Pre-drilling for bored piles at B1(Portion I),
C2-01, C2-02, E2-01, B1(Portion II), B2(Potion II), C1-01 & C1-02(Portion
II), C3-02. -
Bored piling at C3-03b, C3-04b, C2-04b, D1-03,
E1-03, D1-04, E1-04, E2-03, C3-01b, C2-01, B1(Portion 1), C3-04b, E3-01,
C3-01a, C2-03b, C3-03a, C3-04a, D1-02, E1-02, E2-01, D2-01. -
Pile cap construction at E2-01, C4-03, C4-04,
E3-03, D1-01, E1-01, HKY-P02 pile cap & HKYAB ELS. -
Footing construction at C4-01a and C4-01b. (b)
Viaduct Works -
Segment Mould
fabrication and installation. -
Segment production line and segment storage yard establishment -
First batch of precast segment production -
Rebar cage jig fabrication -
Segment shop drawing preparation for bridge C4 -
M.J. S.O.P. erection method statement submission -
Typical pier column mould
fabrication -
Bearing fabrication for bridge C4 and C3 -
Falsework & formwork design for typical pier
head -
Pier column trial panel at CTC yard -
First pair of segment erection method statement -
PT material delivery (first batch) to HZ precast
yard preparation -
Bearing fabrication for bridge C2, C3 and C4 -
Ground beam construction for gantry crane -
Containers site office setup (c)
Jockey Club Road -
Confirmation the retaining wall design and
commence works -
Tree fell and UU diversion -
Completion of gas main diversion and commencement
of cut slope work and soil nail at the 3SW-A/C149 -
Completion of gas main diversion and erection of
temporary steel decking for site access at the 3SW-C/F63 (d)
Tai Wo Service Road West -
Road widening for D2-03 (Jun-Aug) -
Duct laying by telecoms and CLP in the Portion XI
(joint bay) -
Cross road duct laying to refuge island in the
Portion XI -
CLP and gas main duct laying in the Portion XIII -
HKT draw pit construction in the Portion XIII -
Completion of 1650 dia. drain and manhole and
plate load test of retaining
wall FW52 in the Portion XIII -
Commencement of FW52 construction -
ELS and construction of 1650 dia. drain and
manhole in the Portion XVIII -
Erection of temporary barrier -
Demolish of HKY staircase (e)
Tai Wo Service Road East -
Construction of drainage works at Portion XI and
XII -
Water main laying works (f)
Fanling
Highway -
Road works for Diversion of Fanling
Highway for Pier D2-03 Construction |
ND/2019/06 |
(a)
Finishing works and E&M installations for the Management
Office Building (MOB) at Portion 4 (b)
Off-site fabrication of steel column, steel truss and bracing of
steel canopy in China (c)
Erection of the steel members of steel canopy at Portion 3 (d)
Construction of retaining wall FW21 at Portion 6 (e)
Construction of ground slab of the market stall area and concrete
carriageway at Portion 3 (f)
Construction of underground utilities in the final stage market
at Portion 3 (g)
Installation of sheet piles for ELS for footings of additional
carriageway steel cover at Portion 3 |
ND/2019/07 |
(h)
Site clearance at Portion 1 and 2. (i)
Erection of site hoarding at Portion 1. (j)
C&D waste disposal in Portion 1 and 2. (k)
G.I. works at Portion 1. (l)
Construction of box culvert in Portion 2. (m)
Filling works in Portion 2. (n)
Tree felling / Disposal of yard waste in Portion 1 and 2 (o)
Construction of site haul road in Portion 1. (p)
Trial pit at Ma Sik Road. (q)
Demolition of villager’s houses in Portion 1 and 2. (r)
Removal of asbestos containing materials in Portion 1 and 2. |