Table 12.1
Summary Table for Site
Activities, Potential Environmental Impacts and Recommended Mitigation Measures
in the
coming Two Months
Contract No. |
Major
Site Activities (July and August 2021) |
Location/
Working Period |
Potential
Environmental Impact |
Recommended
Mitigation Measures |
ND/2019/01 |
(a) Site clearance |
Portion 1f, 2, 3,
5, 6a, 7, 10b |
- Construction
Dust impact - Noise
Impact (Construction Phase) - Water
Quality Impact (Construction Phase) - Waste
Management (Construction Waste) |
Air -
Regular
watering on exposed worksites and haul road. -
Cover the
stockpiles or dusty materials. -
Deploy
water browsers to water the haul road. -
Deploy
mist-cannon on site -
Install
sprinkler system for dust suppression. -
Provide
shelter with top and 3-sides for cement production activities. -
Entirely
cover the Arsenic-containing soil. -
Store the
bulk cement in enclosed silo tank for Solidification / Stabilization
treatment. -
Close the
mechanical cover of the vehicles used for transporting dusty materials. -
Establish
vehicle wheel washing facilities at vehicle exit points. -
Speed
control of site vehicles. -
Shotcrete
on exposed slope. -
Erect
solid site hoarding. Noise -
Regular
inspect of construction plants in good condition -
Provide
temporary noise screens if necessary. -
Use of
Quiet plants (QPME) and working methods if possible. -
Sequencing
operation of construction plants where practicable. -
Shut down
the machines and plant if not in use. -
Only
well-maintained plant to be operated on-site. -
Mobile
plant to be sited as far away from NSRs as possible and practicable. -
Conduct
noise monitoring regularly. -
Erect
silent-up noise barrier at Portion 6b. Water -
Set up
wastewater treatment system (AquaSed) on site. -
Erect
soil bund / temporary drain to divert /collect surface runoff. -
Maintain
the drainage and wastewater treatment facilities. Waste / Chemical Management -
Sort out
demolition debris and excavated materials from demolition works to recover
reusable / recyclable portions. -
Provide recycling
bin on site, encourage reuse and recycle as much as possible. -
Provide
drip tray for chemical containers. -
Chemical
spill kit available on site. -
Chemical
waste cabinet available on site. -
Chemical
wastes to be stored in appropriate containers and collected by a licensed
chemical waste collector. -
Delivery
of yard waste to Y-Park for reuse or other agreed alternative site (Tung Wah
camp site). |
(b) GI works |
Portion 2, 8b |
|||
(c) Excavation |
Portion 3, 5, 6a, 8a, 9b, 9c, 10a |
|||
(d) Construction of retaining wall |
Portion 5, 6a, 8a |
|||
(e) Soil nailing / shotcrete |
Portion 6a, 8a |
|||
(f) Demolition of existing structure |
Portion 8a |
|||
(g)
Construction
of temporary site haul road |
Portion2, 6a, 1f |
|||
(h)
Pilot
trial for arsenic soil treatment works |
Portion 6b |
|||
(i)
Tree
felling |
Portion 2, 3, 5, 7 |
|||
(j)
Sheetpiling |
Portion 9b, 10a |
|||
|
|
|||
ND/2019/02 |
(a)
Pre-bored Socketed H-pile |
Portion 7, 9, 10 |
Air, Noise,
Water, Waste, Ecology |
-
Dusty works
should be spray water or idle stockpile or slop should be covered by
Tarpaulin sheet properly. -
Plants
should be well maintained to prevent dark smoke and oil leakage. Idle plant
should be turned off. -
Drip tray
should be provided for all chemical and stationary plants. -
No
construction works shall be carried out in restricted hours (7:00 pm to 7:00
am) unless CNP is obtained. -
Waste
should be sorted and dispose according to the Waste Management Plan -
No direct
discharge of wastewater into storm drains is allowed. Wastewater must be
de-silted before discharged in accordance with the water discharge license. -
Dull
green barrier and ecological measures should be implemented according to the
Ecological protection plan. |
(b)
Hoarding erection |
Portion 10 |
Air, Noise,
Waste |
||
(c)
Tree Felling |
Portion 7 |
Air, Noise,
Waste |
||
(d)
ELS |
Portion 1, 9 |
Air, Noise,
Water, Waste, Ecology |
||
ND/2019/03 |
(a)
Excavation
of irrigation channel |
Long Valley |
-
C&D
waste -
Air
pollution -
Noise
pollution |
-
Watering exposed
earth regularly -
Cover
C&D material by tarpaulin -
Adopt
QPME for excavation |
(b)
Excavation
of trench in Yin Kong Road |
Portion 1 and Portion 1A |
-
C&D
waste -
Air
pollution -
Noise
pollution -
Water
pollution |
-
Watering exposed
earth regularly -
Cover
C&D material by tarpaulin -
Noise
barrier for screening from source of noise -
Wastewater
will be treated before discharging to channel |
|
(c)
Demolition
of existing structure |
Long Valley |
-
C&D
material -
Air
Pollution |
-
Cover
C&D material by tarpaulin -
Watering
while demolish the structure |
|
(d)
Construction
works of storage shed and Type 2 Storage House |
Long Valley |
-
C&D
material -
Air
Pollution |
-
Watering
exposed earth regularly -
Cover
C&D material by tarpaulin |
|
(e)
Asbestos Removal
in Long Valley |
Long Valley |
-
Air
Pollution |
-
Removing
the asbestos containing material according to requirement of COP |
|
ND/2019/04 |
(a)
Socket
H-piling |
Portion N |
-
Air, Noise,
Water, Waste |
-
Dusty works
should be sprayed with water or stockpile should be covered by tarpaulin
properly. -
Plants
should have maintenance to prevent dark smoke and oil leakage. Idle plant
should be turned off. -
Drip tray
should be provided for all chemical and stationary plants. -
No
construction works shall be carried out in restricted hours (7:00 pm to 7:00
am) unless CNP is granted. -
Waste
should be sorted and disposed according to Waste Management Plan. -
No direct
discharge of wastewater into storm water drains is allowed. Wastewater must
be desilted before discharging according to water discharge license. |
(b)
Bored
piling |
Bridge A2, F |
-
Air,
Noise, Water, Waste |
||
(c)
Excavation |
Bridge F |
-
Air,
Noise, Waste |
||
(d)
Site
clearance |
Portion A, B |
-
Air,
Noise, Waste |
||
(e)
Tree
felling |
Portion A |
-
Air,
Noise, Waste |
||
ND/2019/05 |
(a)
Ground investigation works |
FLN3-DH016, ABH02, ABH04, D39(P), ABH10 |
-
Construction
Dust Impact -
Noise
Impact -
Water
Quality Impact (Construction Phase) -
Waste
Management (Construction Waste) -
Landscape
and Visual -
Cultural
Heritage |
-
Regular
watering on exposed worksites and haul road -
Stockpiling
area should be provided with covers and water spraying system -
Only well-maintained
plant to be operated on-site -
Plant
known to emit noise strongly in one direction, where possible, be orientated
so that the noise is directed away from nearby NSRs; -
Mobile
plant to be sited as far away from NSRs as possible practicable -
All open
stockpiles of construction materials
of more than 50m3 to be covered with tarpaulin -
Manholes
to be adequately covered and temporarily sealed so as to prevent silt,
construction materials or debris being washed into the drainage system -
All
vehicles and plant to be cleaned before leaving a construction site to ensure
no earth, mud, debris and the like is deposited by them on roads. -
Segregate
and store different types of waste in different containers, skip or
stockpiles to enhance reuse or recycling of materials and their proper
disposal -
Sort out
demolition debris and excavated materials from demolition works to recover
reusable/recyclable portions -
Provide training
to workers on appropriate waste management procedures, including waste
reduction, reuse and recycling -
To adopt
other good site practice, such as arrangements for collection and effective
disposal to an appropriate facility, of all wastes generated at the site and
regular cleaning and maintenance programme for drainage -
Chemical
wastes to be stored in appropriate containers and collected by a licensed
chemical waste Contractor. Chemical wastes (e.g. spent lubricant oil) should
be recycled at an appropriate facility as far as possible, while the chemical
waste that cannot be recycled should be disposed of at either the Chemical
Waste Treatment Centre, or another licensed facility, in accordance with the
Waste Disposal (Chemical Waste) (General) Regulation -
Conducting
Construction Vibration Monitoring -
Tree Protection & Preservation – Exiting
trees to be retained within the Project site should be carefully protected
during construction. In particular OVTs will be preserved according to ETWB
Technical Circular (Works) No. 29/2004. -
Tree Transplantation – Tree unavoidably affected
by the Project works should be transplanted where practical. Tree should be
transplanted straight to their final receptor site and not held in a
temporary nursey as far as possible. -
Erect 2m high dull green site boundary fence. -
Light Control – Construction day and night time
should be controlled to minimize glare impact to adjacent VSRs during the
Construction phase. |
(b)
Pre drilling for bored piles |
B1 (Portion I), C2-01, C2-02, E2-01,
B1 (Portion II), B2 (Portion II), C1-01 & C1-02 (Portion II), C3-02 |
|||
(c)
Bored piling |
C3-03b, C3-04b, C2-04B, D1-03, E1-03, D1-04,
E1-04, E2-03, C3-01b, C2-01, B1(Portion 1), C3-04b, E3-01, C3-01a, C2-03b,
C3-03a, C3-04a, D1-02, E1-02, E2-01, D2-01. |
|||
(d) Soil
Nail |
Jockey Club Road |
|||
(e)
Pile Cap Construction |
E2-01, C4-03, C4-04, E3-03, D1-01, E1-01,
HKY-P02 pile cap & HKY-AB ELS. C4-01a and C4-01b |
|||
(f)
Footing Construction |
HKYFB Cap P-02 and Cap AB |
|||
(g)
Site
Formation |
Portion XI, XII, TWSRW |
|||
(h) Utitilies Diversion Works and
Permanent Road Works |
TWSRW |
|||
(i)
Tree work
|
TWSRW, Jockey
Club Road |
|||
(j)
TTA |
Jockey Club
Road |
|||
(k) Drainage
& Water Mains construction |
Box culvert
BC5, TWSRE |
|||
(l)
UU diversion |
Tai Wo Service
Road West |
|||
(m)
Gas main
diversion |
Jockey Club Road |
|||
(n)
Road works for temporary road diversion |
D2-03, Portion XI |
|||
(o) Retaining
wall construction |
FW04, FW05, FW06, FW52 |
|||
(p) Slope
construction |
C363, FS04, Jockey Club Road |
|||
(q)
Footbridge staircase demolition |
Ho Ka Yuen Footbridge |
|||
ND/2019/06 |
(a)
Construction
of finishing works and E&M works for the Management Office Building (MOB) |
Portion 4 |
-
Noise
pollution - Water pollution |
-
Adopt
noise barrier in screening noise -
Wastewater
generated after wheel washing of vehicles should be treated properly
before discharge |
(b)
Construction of retaining wall FW21 and ramp
structure |
Portion 3 |
-
Water
pollution |
-
Wastewater
generated after wheel washing of vehicles should be treated properly before
disposal -
Provide
sand bags for prevent polluted water discharge off site without wastewater
treatment |
|
(c)
Erection
of the steel members of steel canopy; Construction of ground slab of the market
stall area and concrete carriageway; Construction of underground utilities in
the final stage market |
Portion 3 |
-
C&D
waste -
Air
pollution -
Noise
pollution -
Water
pollution |
-
Cover
C&D waste by impervious sheeting -
Spray
with water to work area before, during and after the work -
Adopt
QPME for excavator -
Wastewater
generated after wheel washing of vehicles should be treated properly before
disposal |
|
|
(d)
Installation
and Construction of sheet piles for ELS for footings of additional
carriageway steel cover |
Portion 3 |
-
C&D
waste -
Air
pollution -
Noise
pollution -
Water
pollution |
-
Cover
C&D waste by impervious sheeting -
Spray with
water to work area before, during and after the work -
Adopt
QPME for excavator -
Wastewater
generated after wheel washing of vehicles should be treated properly before
disposal |
ND/2019/07 |
(a)
Site clearance |
Portion 1, Portion 2 |
-
Construction
Dust Impact -
Noise
Impact -
Water
Quality Impact (Construction Phase) -
Waste
Management (Construction Waste) -
Landscape
and Visual |
-
Regular
watering on exposed worksites and haul road. -
Stockpiling
area should be provided with covers and water s praying system. -
Only well
maintained plant to be operated on site. -
Plant
known to emit noise strongly in one direction, where possible, be orientated
so that the noise is directed away from nearby NSRs. -
Mobile
plant to be sited as far away from NSRs as possible practicable. -
All open
stockpiles of construction materials of more than 50m3 to be
covered with tarpaulin. -
Manholes
to be adequately covered and temporarily sealed so as to prevent silt,
construction materials or debris being washed into the drainage system. -
All
vehicles and plant to be cleaned before leaving a construction site to ensure
no earth, mud, debris and the like is deposited by them on roads. -
Segregate
and store different types of waste in different containers, skip or
stockpiles to enhance reuse or recycling of materials and their proper
disposal. -
Sort out
demolition debris and excavated materials from demolition works to recover
reusable/recyclable portions. -
Provide
training to workers on appropriate waste management procedures, including
waste reduction, reuse and recycling. -
To adopt
other good site practice, such as arrangements for collection and effective disposal
to an appropriate facility, of all wastes generated at the site and regular
cleaning and maintenance programme for drainage. -
Chemical
wastes to be stored in appropriate containers and collected by a licensed
chemical waste Contractor. Chemical wastes (e.g. spent lubricant oil) should
be recycled at an appropriate facility as far as possible, while the chemical
waste that cannot be recycled should be disposed of at either the Chemical
Waste Treatment Centre, or another licensed facility, in accordance with the
Waste Disposal (Chemical Waste) (General) Regulation. -
Tree
Protection & Preservation – Existing trees to be retained within the
Project Site should be carefully protected during construction. In particular
OVTs will be preserved according to ETWB Technical Circular (Works) No.
29/2004. -
Tree
Transplantation Trees unavoidably affected by the Project works should be
transplanted where practical. Trees should be transplanted straight to their
final receptor site and not held in a temporary nursery as far as possible. -
Erect 2m
high dull green site boundary fence. -
Light
Control Construction day and night time lighting should be controlled to
minimize glare impact to adjacent VSRs during the Construction phase. |
(b)
Erection of site hoarding |
Portion 1 |
|||
(c)
C&D waste disposal |
Portion 1, Portion 2 |
|||
(d)
Ground investigation works |
Portion 1 |
|||
(e)
Construction of box culvert |
Portion 2 |
|||
(f)
Filing works |
Portion 2 |
|||
(g)
Tree felling/ disposal of yard waste |
Portion 1, Portion 2 |
|||
(h)
Construction of site haul road |
Portion 1 |
|||
(i)
Trial pit |
Ma Sik Road |
|||
(j)
Demolition of villager’s houses |
Portion 1, Portion 2 |