Table 10.4 Specific Water
Quality Mitigation Measures for Major Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|||
ND/2019/01 |
Temporary wastewater
storage tank for storm water retention |
Hydroseeding for
stockpile area |
||
ND/2019/02 |
Provision of sand
bags around works area |
Covering exposed slope surface by tarpaulin |
||
ND/2019/03 |
Wastewater from wheel
washing was directed to wastewater treatment facility |
Regular clearance of
water for wheel washing facility |
||
ND/2019/04 |
Surface channels and
earth bunds to direct storm water to wastewater treatment facilities for
works area near Siu Hang San Tsuen Stream |
Provision of
wastewater treatment facilities for works area near Siu Hang San Tsuen Stream
|
Deployment of silt
curtain around works area in Ng Tung River |
|
ND/2019/05 |
Deployment of sand
bags around works area |
Smart checking operation of wastewater
treatment facilities |
||
ND/2019/06 |
Grasscrete for slope protection |
Provision of concrete berm around site area |
||
ND/2019/07 |
Covering exposed slope surface by tarpaulin |
Additional wastewater