EXECUTIVE SUMMARY

Introduction

1.      This is the 20th monthly Environmental Monitoring and Audit (EM&A) Report under First Phase Development of Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs), comprising the Advance Works and First Stage Works (the Project). This report was prepared by Wellab Limited under “Service Contract No. NDO 04/2019 Environmental Team for Environmental Monitoring and Audit Works in Construction Phase for the First Phase Development of KTN and FLN NDAs” (hereinafter called the “Service Contract”). This report documents the findings of Environmental Monitoring and Audit (EM&A) work conducted in June 2021.

 

2.      During the reporting month, the following Works Contracts under relevant Environmental Permit(s) were undertaken for the Project:

 

Table I             Works Contracts under relevant Environmental Permit(s) in the Reporting Month

Works Contracts

Environmental Permit No.

Designated Project (DP)

Commencement date of construction

Contract No. ND/2019/01 - Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works

EP-466/2013

Castle Peak Road Diversion

12th August 2020

EP-467/2013/A

Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement

12th August 2020

EP-468/2013/A

Kwu Tung North New Development Area Road D1 to D5

 

1st June 2020

EP-470/2013

Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works

 

23rd March 2020

Contract No. ND/2019/02 - Kwu Tung North New Development Area, Phase 1: Roads and Drains between Kwu Tung North New Development Area and Shek Wu Hui

 

EP-469/2013

Sewage Pumping Stations in Kwu Tung North New Development Area

28th October 2020

Contract No. ND/2019/03 - Kwu Tung North New Development Area, Phase 1: Development of Long Valley Nature Park

EP-468/2013/A

Kwu Tung North New Development Area Road D1 to D5

3rd July 2020

EP-473/2013/A

Fanling Bypass Eastern Section (New Road)

6th October 2020

Contract No. ND/2019/04 –

Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shek Wu San Tsuen North to Lung Yeuk Tau)

EP-473/2013/A

 

Fanling Bypass Eastern Section (New Road)

23rd February 2021

EP-546/2017

Fanling North Temporary Sewage Pumping Station

16th February 2021

Contract No. ND/2019/05 -

Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shung Him Tong to Kau Lung Hang)

EP-473/2013/A

Fanling Bypass Eastern Section (New Road)

1st August 2020

Contract No. ND/2019/06 - Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

EP-475/2013/A

Reprovision of temporary Wholesale Market in Fanling North New Development Area

29th October 2019

Contract No. ND/2019/07 –

Fanling North New Development Area, Phase 1: Site Formation and Infrastructure Works

Works area not under relevant Environmental Permit for Phase 1 of the Project.

1st March 2021

Environmental Monitoring and Audit Progress

3.      A summary of the EM&A activities in this reporting month is listed in Table II below:

 

Table II  Summary Table for EM&A Activities in the Reporting Month

EM&A Activities

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/04

ND/2019/05

ND/2019/06

ND/2019/07

1-hr Total Suspended Particulates (TSP) Monitoring

2, 8, 11, 17, 23, 29

June 2021

N/A

1, 2, 7, 8, 10, 11, 16, 17, 22, 23, 28, 29

June 2021

1, 2, 7, 8, 10, 11, 16, 17, 22, 23, 28, 29

June 2021

1, 7, 10, 16, 22, 28 June 2021

N/A

 

N/A

 

24-hr TSP Monitoring

2, 8, 11, 17, 23, 29

June 2021

N/A

2, 3, 8, 9, 11, 15, 17, 21, 23, 25, 29, 30

June 2021

2, 3, 8, 9, 11, 15, 17, 21, 23, 25, 29, 30

June 2021

3, 9, 15, 21, 25, 30 June 2021

N/A

N/A

24-hr RSP (Ambient Arsenic) Monitoring for Land Contamination

1, 7, 10, 16, 22, 28 June 2021

N/A

1, 7, 10, 16, 22, 28 June 2021

N/A

N/A

N/A

N/A

Noise Monitoring

2, 11, 17, 23, 29 June 2021

N/A

1, 7, 16, 22 June 2021

N/A

Water Quality Monitoring

N/A

2, 4, 7, 9, 11, 15, 17, 19, 21, 23, 25, 28, 30 June 2021

N/A

2, 4, 7, 9, 11, 15, 17, 19, 21, 23, 25, 28, 30 June 2021

N/A

N/A

N/A

Landfill Gas

Monitoring

22 June 2021

N/A

N/A

N/A

N/A

N/A

N/A

 

Built Heritage Monitoring

N/A

N/A

N/A

N/A

Daily assessment subject to construction works conducted within assessment area

N/A

N/A

 

Ecologic-al Survey

Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue

River, and Long Valley

N/A*

N/A*

2, 3, 10, 11, 15, 17, 21, 24, 28, 30 June 2021

2, 10, 15, 24, 28, June 2021

N/A*

N/A*

N/A*

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream

22 June 2021

N/A*

22 June 2021

22 June 2021

N/A*

N/A*

N/A*

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

9, 18 June 2021

9, 18 June 2021

9 June 2021

9 June 2021

9 June 2021

N/A*

N/A*

Environmental Site Inspection

1, 8, 16, 22, 29 June 2021

2, 9, 16, 23, 30 June 2021

4, 11, 18, 22 June 2021

3, 10, 17, 24 June 2021

9, 15, 21, 28 June 2021

3, 10, 17, 24, 30 June 2021

4, 9, 18, 25 June 2021

Remark:

N/A – No relevant monitoring is required according to updated EM&A Manual

N/A* – No relevant monitoring is required according to Baseline Ecological Monitoring Plan (Table 3.1)

[1] Since the distance between monitoring station CP-KTN-NMS2 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03

[2] Since the distance between monitoring station CP-KTN-NMS3 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03

[3] Since the distance between monitoring station CP-KTN-NMS1 and site boundary of ND/2019/02 under EP-469/2013 exceeds 300m. The monitoring station is not applicable to ND/2019/02

[4] Since the distance between monitoring station FLN-DMS1 and site boundary of ND/2019/05 under EP-473/2013/A exceeds500m. The monitoring station is not applicable to ND/2019/05

[5] Since the distance between monitoring station FLN-DMS3 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 500m. The monitoring station is not applicable to ND/2019/03 and ND/2019/04

[6] Since the distance between monitoring station FLN-DMS5 and site boundary of ND/2019/05 under EP-473/2013/A exceeds 500m. The monitoring station is not applicable to ND/2019/05

[7] Since the distance between monitoring station CP-FLN-NMS2 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03 and ND/2019/04.

[8] Since the distance between monitoring station CP-FLN-NMS1 and site boundary of ND/2019/03 under EP-473/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03.

Breaches of Action and Limit Levels

 

4.      Summary of the environmental exceedances of the reporting month is tabulated in Table III.

 

Table III   Summary Table for Events Recorded in the Reporting Month

Environmental Monitoring

Parameter

No. of non-project related Exceedances

Total No. of non-project related Exceedances

No. of Exceedance related to the Construction Works of the Contract

Total No. of Exceedance related to the Construction Works of the Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

 

 

 

0

0

0

0

24-hr TSP

0

0

 

 

 

0

0

0

0

24-hr RSP

(Ambient Arsenic)

0

0

 

 

 

0

0

0

0

Noise

Leq(30min)

0

0

 

 

 

0

0

0

0

Water Quality[1]

DO

1

12

13

0

3

3

Turbidity

0

5

5

0

3

3

SS

0

4

4

0

3

3

Arsenic

3

0

3

0

0

0

 

Landfill Gas

O2

0

0

 

0

0

0

0

CH4

CO2

Cultural heritage

Built Heritage Monitoring

0

0

0

0

0

0

Remark:

[1] The Action and Limit Levels for the Additional Water Quality Monitoring is subject to the agreement with the authority.

 

Air Quality

 

5.      All construction air quality monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Construction Noise 

 

6.      All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Water Quality

 

7.      All additional water quality monitoring was conducted as scheduled in the reporting month. One (1) Action Level exceedance and fifteen (15) Limit Level exceedances for dissolved oxygen, eight (8) Limit level exceedances for turbidity, seven (7) Limit Level exceedances for suspended solids and three (3) Action Level exceedance for arsenic of impact water quality monitoring were recorded. After investigation, three (3) Limit Level exceedances for dissolved oxygen, three (3) Limit level exceedances for turbidity and three (3) Limit Level exceedances for suspended solids at monitoring station, SHST-IS2, were found due to Contract No. ND/2019/04. Other exceedances were considered non-projected related. No construction of channel for alternation of natural streams was carried out in the reporting month. Therefore, no water quality monitoring according to pre-construction ET’s Updated EM&A Manual and Baseline Water Quality Monitoring Report (KTN & FLN NDA) was conducted. For the details, please refer to Section 5.

 

Land Contamination

 

8.      All ambient arsenic monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Landfill Gas Monitoring

 

9.      Monitoring of landfill gases in the reporting month was carried out by the Contractor under ND/2019/01 at excavation location, Portion 6b. No Limit Level exceedance was recorded.

 


 

Built Heritage Monitoring

 

10.  Built heritage monitoring in the reporting month was carried out by the Contractor under ND/2019/05 for surveyed cultural heritage. No Limit Level exceedance was recorded.

 

Ecological Monitoring

 

11.  All ecological monitoring was conducted as scheduled in the reporting month. Action and limit level will be compared after the issue of Final Baseline Ecological Report. The ecological monitoring result in the Reporting Month is shown in Appendix L.

 

Complaint Log

 

12.  No environmental complaint was received in the reporting month.

 

Notification of Summons and Successful Prosecutions

 

13.  No notification of summons or successful prosecutions was received in the reporting month.

Reporting Changes

 

14.  This report has been prepared in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the “Updated Environmental Monitoring and Audit Manual for Advance and First Stage Works of Kwu Tung North and Fanling North New Development Areas” (Updated EM&A Manual).

Future Key Issues

15.  The major site activities for the coming two months are shown in Table IV.

Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (July 2021 and August 2021)

ND/2019/01

 

(a)          Site clearance, site formation and additional road opening in Portion 1f

(b)         Site clearance, ground investigation, tree felling and temporary road construction in Portion 2

(c)          Site clearance, excavation, sheetpiling and excavation, and pipes laying in Portion 3

(d)         Site clearance, stockpile of soil, construction of KW01 retaining wall, sheetpiling and excavation, pipes laying, and tree felling in Portion 5

(e)          Site Clearance, sheetpiling and excavation, pipes laying, backfilling, construction of KW01 retaining wall, construction of KB01 retaining wall, and haul road construction in Portion 6a

(f)          Arsenic soil treatment works in Portion 6b

(g)         Site clearance, sheetpiling and excavation, pipes laying in Portion 7

(h)         Construction of retaining wall, slope cutting, soil nailing, slope drainage and maintenance access construction, excavation for Fresh Water Service Reservoir, RC construction of Flushing Water Service Reservoir in Portion 8a

(i)           Sheetpiling for jacking pit, trenchless works and excavation in Portion 8b

(j)           Sheetpiling and excavation, pipes laying of existing structures in Portion 9b

(k)         Stockpile of soil and excavation in Portion 9c

(l)           Excavation, sheetpiling for ELS, pipes laying, noise barrier footing  in Portion 10a

(m)       Sheetpiling and excavation, pipes laying in Portion 10b

(n)         Construction of MBR at 11b

(o)         Construction of temporary sewage pumping station in Portion 14

ND/2019/02

(a)          Pre-bored Socketed H-pile

(b)         Tree felling

(c)          ELS

(d)         Hoarding erection

ND/2019/03

 

(a)        Underground Utilities Laying in Portion 1;

(b)       Portion 2 to Portion 20

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Geotechnical Works in Long Valley (Trail Pits)

-          Construction of Temporary Road in Long Valley

-          Asbestos Removal in Long Valley

-          Demolition of Existing Construction in Handed over Area

-          Construction of Type 2 Storage House

-          Construction of Outdoor Composting Facility

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Construction of Storage Sheds

-          Wetland Creation & Restoration works

ND/2019/04

 

(a)           Site clearance

(b)           Tree felling

(c)           Predrill

(d)           Socket H-piling

(e)           Bored piling

(f)            Excavation

(g)           ELS 

ND/2019/05

(a)           Bridge Foundation Works

-          Ground investigation works at FLN3-DH016, ABH02, ABH04, ABH10, D39(P).

-          Pre-drilling for bored piles at B1(Portion I), C2-01, C2-02, E2-01, B1(Portion II), B2(Potion II), C1-01 & C1-02(Portion II), C3-02.

-          Bored piling at C3-03b, C3-04b, C2-04b, D1-03, E1-03, D1-04, E1-04, E2-03, C3-01b, C2-01, B1(Portion 1), C3-04b, E3-01, C3-01a, C2-03b, C3-03a, C3-04a, D1-02, E1-02, E2-01, D2-01.

-          Pile cap construction at E2-01, C4-03, C4-04, E3-03, D1-01, E1-01, HKY-P02 pile cap & HKYAB ELS.

-          Footing construction at C4-01a and C4-01b.

(b)          Viaduct Works

-          Segment Mould fabrication and installation.

-          Segment production line and segment storage yard establishment

-          First batch of precast segment production

-          Rebar cage jig fabrication

-          Segment shop drawing preparation for bridge C4

-          M.J. S.O.P. erection method statement submission

-          Typical pier column mould fabrication

-          Bearing fabrication for bridge C4 and C3

-          Falsework & formwork design for typical pier head

-          Pier column trial panel at CTC yard

-          First pair of segment erection method statement

-          PT material delivery (first batch) to HZ precast yard preparation

-          Bearing fabrication for bridge C2, C3 and C4

-          Ground beam construction for gantry crane

-          Containers site office setup

(c)           Jockey Club Road

-          Confirmation the retaining wall design and commence works

-          Tree fell and UU diversion

-          Completion of gas main diversion and commencement of cut slope work and soil nail at the 3SW-A/C149

-          Completion of gas main diversion and erection of temporary steel decking for site access at the 3SW-C/F63

(d)          Tai Wo Service Road West

-          Road widening for D2-03 (Jun-Aug)

-          Duct laying by telecoms and CLP in the Portion XI (joint bay)

-          Cross road duct laying to refuge island in the Portion XI

-          CLP and gas main duct laying in the Portion XIII

-          HKT draw pit construction in the Portion XIII

-          Completion of 1650 dia. drain and manhole and plate load test of         retaining wall FW52 in the Portion XIII

-          Commencement of FW52 construction

-          ELS and construction of 1650 dia. drain and manhole in the Portion XVIII

-          Erection of temporary barrier

-          Demolish of HKY staircase

-          Tree felling at 3SW-D/C78 and TCSS duct laying

(e)           Tai Wo Service Road East

-          Construction of drainage works at Portion XI and XII 

-          Water main laying works 

-          Construction of HKY Footbrige LT1 lift & P02 column

-          Road works at Potion XI

(f)           Fanling Highway

-          Road works for Diversion of Fanling Highway for Pier D2-03 Construction

ND/2019/06

(a)          Finishing works and E&M installations for the Management Office Building (MOB) at Portion 4.

(b)         Off-site fabrication of steel column, steel truss and bracing of steel canopy in China.

(c)          Erection of the steel members of steel canopy at Portion 3.

(d)         Construction of retaining wall FW21 at Portion 6.

(e)          Construction of ground slab of the market stall area at Portion 3.

(f)          Construction of underground utilities in the final stage market at Portion 3.

(g)         Installation of sheet piles for ELS for footings of additional carriageway steel cover at Portion 3.

(h)         Construction of footings of additional carriageway steel cover at Portion 3.

ND/2019/07

(a)        Site clearance at Portion 1 and 2.

(b)        Erection of site hoarding at Portion 1.

(c)        C&D waste disposal at Portion 1 and 2.

(d)        G.I. works at Portion 1.

(e)        Construction of box culvert at Portion 2.

(f)         Filling works at Portion 2.

(g)        Tree felling/ Disposal of yard waste at Portion 1 and 2.

(h)        Construction of site haul road at Portion 1.

(i)         Trial pit at Ma Sik Road.

(j)         Demolition of villagers houses at Portion 1 and 2.

(k)        Removal of asbestoses containing material at Portion 1 and 2.