13.1 This
Monthly EM&A Report presents the EM&A work undertaken in January 2021
in accordance with Updated EM&A Manual.
13.2
Two Action
Level exceedance for construction noise monitoring was recorded due to the
documented noise complaint received for Contract ND/2019/02 and ND/2019/05 and
no exceedance of Limit Level for construction noise monitoring was recorded in
this reporting month.
13.3
No Action/Limit Level exceedance were
recorded for air quality, ambient arsenic, landfill gas monitoring and build
heritage monitoring in the reporting month.
Contract No. ND/2019/01
13.4
Environmental
site inspection were conducted on 5th, 12th,
19th, 26th, January 2021 by ET in the reporting month.
Contract No. ND/2019/02
13.5
Environmental
site inspection were conducted on 6th, 13th,
22nd, 27th January 20201 by ET in the reporting month.
Contract No. ND/2019/03
13.6
Environmental
site inspection were conducted on 8th, 15th,
22nd, 29th January 2021 by ET in the reporting month.
Contract No. ND/2019/05
13.7
Environmental
site inspections were conducted on 4th,
13th, 18th, 25th January 2021 by ET in the reporting month.
Contract No. ND/2019/06
13.8
Environmental
site inspections were conducted on 6th,
11th, 21st, 28th January 2021 by ET in the reporting month.
13.9
There
was four environmental complaints, no notification of summons or successful prosecutions
received in the reporting month.
13.10
The
ET would keep track on the EM&A programme to ensure compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures.
13.11 According
to the environmental audits performed in the reporting month, the following
recommendations were made:
Air
Quality Impact
¡P To
enhance the dust suppression measures such as water spraying on all haul roads
and exposed work site area;
¡P To
maintain the impervious material to entirely cover the stockpile of dusty materials;
¡P To
ensure all regulated machines displayed with valid Non-road Mobile Machinery
(NRMM) labels; and
¡P To
keep public road near work site area clean and free of dust.
Water Impact
¡P To
prevent any surface runoff discharge into nearby drainage or stream;
¡P To
divert all the water generated from construction site to de-silting facilities
with enough handling capacity before discharge;
and
¡P To
ensure the drainage facilities would not be clogged with waste to avoid
overflow.
Waste/Chemical Management
¡P To
properly dispose of general refuse on site;
¡P To
avoid improper handling, storage and disposal of oil drums or chemical
containers on site; and
¡P To
store chemical waste/waste oil properly in the designated place before
disposal.
Landscape
& Visual Impact
¡P To
clear the construction materials/wastes properly within the tree protection
zone.
¡P Retained
trees should be carefully protected.
¡P Dull green fencing should be secured with no gaps
or no holes.
Landfill
Gas Hazard
¡P ¡§No Smoking¡¨ and ¡§No Naked Flame¡¨ notices in
Chinese and English should be posted prominently around the construction site.
Land
Contamination
¡P Stockpiling site(s) should be lined with
impermeable sheeting and bunded. Stockpiles should be properly covered by
impermeable sheeting to reduce dust emission during dry season or contaminated
run-off during rainy season. Watering should be avoided on stockpiles of soil
to minimize runoff.