Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (February 2021 and March 2021)

ND/2019/01

 

(a)           Site clearance and site formation in Portion 1f;

(b)           Site clearance, ground investigation, working platform erection for soil nail, soil nailing in Portion 2

(c)           Site clearance and ground investigation in Portion 3

(d)          Erection of temporary noise barrier steel frame and laying of rising mains in Portion 4

(e)           Site clearance, temporary slope cutting for temporary soil nailing, Stockpile of soil, Ground Investigation, construction of KW01 retaining wall in Portion 5

(f)            Site Clearance, temporary slope cutting for temporary soil nailing, sheetpiling and excavation, pipes laying, backfilling, pre-bored H-piling, construction of KW01 retaining wall, construction site haul road in Portion 6a

(g)           Arsenic soil treatment works in Portion 6b

(h)           Site Clearance, Construction of temporary road for alternative Po Lau Road, Construction of site accommodation in Area T2 and T3 , sheetpiling and excavation, pipes laying in Portion 7

(i)            Ground Investigation, Construction of Retaining Wall, slope cutting, soil nailing, slope drainage and maintenance access construction, Excavation for Fresh Water Service Reservoir, RC construction of Flushing Water Service Reservoir in Portion 8a

(j)            Ground Investigation in Portion 8b

(k)           Site clearance, ground investigation and trial pits in Portion 9b

(l)            Stockpile of soil in Portion 9c

(m)         Excavation, sheetpiling for ELS, pipes laying in Portion 10a

(n)           Site Clearance in Portion 10b

(o)           Laying of rising mains in in Portion 11b

(p)           Site clearance, Construction of temporary sewage pumping station, laying of rising mains in Portion 14

(q)           Site clearance, Construction of CLC in Portion 16

ND/2019/02

(a)           Pipe Jacking

(b)           Tree felling

(c)           Inspection Pit

(d)          Hoarding and Dull green barrier erection

(e)           Pre-bored Socketed H-pile

ND/2019/03

 

(a)         Road and Drainage work in Portion 1;

(b)         Portion 2 to Portion 20

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Geotechnical Works in Long Valley (Trail Pits)

-          Construction of Temporary Road in Long Valley

-          Asbestos Removal in Long Valley

-          Demolition of Existing Construction in Handed over Area

-          Construction works of storage shed and type 2 Storage House

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Wetland Creation & Restoration works after Obtaining Approval from AFCD

(c)         Portion 22 and Portion 27

-          Planting at Portion 22

ND/2019/05

(a)         Ground investigation works

(b)         Pre-drilling for bored poles

(c)         Bored oiling

(d)        Socketed H-pile installation

(e)         Construction of haul road

(f)          Construction of footpath

(g)         Footing construction

(h)         Site formation

(i)          Utilities diversion works

(j)          Project Manager¡¦s site accommodation construction

(k)         Tree transplant

(l)          TTA

(m)       Drainage & water mains construction

(n)         Temporary removal of noise barrier and sign gantry 

(o)         UU diversion

(p)         Rockfill slope construction

(q)         Road works for temporary road diversion

(r)          Retaining wall construction

(s)          Slope construction

(t)          Footbridge staircase demolition

ND/2019/06

 

(a)           Construction of finishing works, E&M works and Building Services works of Management Office Building (MOB) at Portion 4.

(b)           Installation of truss of steel canopy at Portion 3.

(c)           Drainage works in the final stage market at Portion 3.

(d)          Formation of carriageway and footway at Portion 3.

(e)           Off-site fabrication, welding and application of coating of columns and steel truss of steel canopy in China.

(f)            Slope improvement works at Portion 6.

(g)           Mobilization of plants for mini-pile works at Portion 3 and 5.

(h)           Commencement of mini-pile works at Portion 3 and 5.