Table IV Summary Table for Site Activities in the coming Two
Months
Contract
No. |
Site
Activities (February 2021 and March 2021) |
ND/2019/01 |
(a)
Site clearance and site
formation in Portion 1f; (b)
Site clearance, ground
investigation, working platform erection for soil nail, soil nailing in
Portion 2 (c)
Site clearance and ground
investigation in
Portion 3 (d)
Erection
of temporary noise barrier steel frame and laying of rising mains in Portion
4 (e)
Site clearance, temporary slope
cutting for temporary soil nailing, Stockpile of soil, Ground Investigation,
construction of KW01 retaining wall in Portion 5 (f)
Site
Clearance, temporary slope cutting for temporary soil nailing, sheetpiling and excavation, pipes laying, backfilling,
pre-bored H-piling, construction of KW01 retaining wall, construction site
haul road in Portion 6a (g)
Arsenic
soil treatment works in Portion 6b (h)
Site
Clearance, Construction of temporary road for alternative Po Lau Road,
Construction of site accommodation in Area T2 and T3 , sheetpiling
and excavation, pipes laying in Portion 7 (i)
Ground
Investigation, Construction of Retaining Wall, slope cutting, soil nailing,
slope drainage and maintenance access construction, Excavation for Fresh
Water Service Reservoir, RC construction of Flushing Water Service Reservoir
in Portion 8a (j)
Ground
Investigation in Portion 8b (k)
Site clearance, ground investigation and trial pits in Portion 9b (l)
Stockpile
of soil in Portion 9c (m)
Excavation,
sheetpiling for ELS, pipes laying in Portion 10a (n)
Site
Clearance in Portion 10b (o)
Laying of rising mains in in Portion 11b (p)
Site clearance, Construction of temporary sewage
pumping station, laying of rising mains in Portion 14 (q)
Site clearance, Construction of CLC in Portion 16 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Tree
felling (c)
Inspection
Pit (d)
Hoarding and
Dull green barrier erection (e)
Pre-bored
Socketed H-pile |
ND/2019/03 |
(a)
Road
and Drainage work in Portion 1; (b)
Portion 2
to Portion 20 -
Erection
of Permanent Boundary Structure -
Construction
of Irrigation Channel -
Geotechnical
Works in Long Valley (Trail Pits) -
Construction
of Temporary Road in Long Valley -
Asbestos
Removal in Long Valley -
Demolition
of Existing Construction in Handed over Area -
Construction
works of storage shed and type 2 Storage House -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Wetland
Creation & Restoration works after Obtaining Approval from AFCD (c)
Portion
22 and Portion 27 -
Planting at Portion 22 |
ND/2019/05 |
(a)
Ground investigation works (b)
Pre-drilling for bored poles (c)
Bored oiling (d)
Socketed H-pile installation (e)
Construction of haul road (f)
Construction of footpath (g)
Footing construction (h)
Site formation (i)
Utilities diversion works (j)
Project Manager¡¦s site accommodation construction
(k)
Tree transplant (l)
TTA (m) Drainage & water mains construction (n)
Temporary removal of noise barrier and sign
gantry (o)
UU diversion (p)
Rockfill slope construction (q)
Road works for temporary road diversion (r)
Retaining wall construction (s)
Slope construction (t)
Footbridge staircase demolition |
ND/2019/06 |
(a)
Construction of finishing
works, E&M works and Building Services works of Management Office
Building (MOB) at Portion 4. (b)
Installation of truss of
steel canopy at Portion 3. (c)
Drainage works in the final
stage market at Portion 3. (d)
Formation of carriageway
and footway at Portion 3. (e)
Off-site fabrication,
welding and application of coating of columns and steel truss of steel canopy
in China. (f)
Slope improvement works at
Portion 6. (g)
Mobilization of plants for
mini-pile works at Portion 3 and 5. (h)
Commencement of mini-pile
works at Portion 3 and 5. |