Table 10.2
Observations and Recommendations during Site Audits |
|||
|
Date |
Observations and
Recommendations |
Follow-up |
Contract No.: ND/2019/01 Date Observations and
Recommendations Follow-up |
|||
Air Quality |
29/12/2020 |
To replace the impervious materials for covering
and sheltering stock of more than 20 bags of cement on top and 3 sides. (Portion
5) |
Improvement/Rectification was
observed during follow-up audit session on 5 January 2021. |
12/01/2021 |
NRMM Label was observed faded, Contractor was reminded to replace the
NRMM Label. |
Improvement/Rectification was
observed during follow-up audit session on 19 January 2021. |
|
26/01/2021 |
To avoid cement from extending beyond storage area for preventing
dust generation. (Portion 8) |
Follow-up action is needed to be
reported in the following month. |
|
Waste/ Chemical Management |
29/12/2020 |
Drip tray should be provided for chemical storage at Portion 8a. |
Improvement/Rectification was
observed during follow-up audit session on 5 January 2021. |
29/12/2020 |
To provide adequate capacity of storage area with drip trays for
chemical storage. (Portion 5) |
Improvement/Rectification was
observed during follow-up audit session on 5 January 2021. |
|
05/01/2021 |
Drip tray should be provided for chemical storage. |
Improvement/Rectification was
observed during follow-up audit session on 12 January 2021. |
|
19/01/2021 |
Drip tray should be provided for chemical storage. |
Improvement/Rectification was
observed during follow-up audit session on 26 January 2021. |
|
Contract
No.: ND/2019/02 |
|||
Air Quality |
06/01/2021 |
Contractor was reminded to water the exposed
worksites regularly to avoid dust generation. |
Improvement/Rectification
was observed during follow-up audit session on 13 January 2021. |
06/01/2021 |
NRMM Label was observed faded, Contractor was
reminded to replace the NRMM Label. |
Improvement/Rectification
was observed during follow-up audit session on 13 January 2021. |
|
13/01/2021 |
NRMM Label was observed faded, Contractor was
reminded to replace the NRMM Label. |
Item
was remarked as 210122-R01. Follow-up action is needed to be reviewed. |
|
22/01/2021 |
NRMM Label was observed faded, Contractor was
reminded to replace the NRMM Label. |
Improvement/Rectification
was observed during follow-up audit session on 27 January 2021. |
|
22/01/2021 |
Contractor was reminded to clean the road
regularly. |
Improvement/Rectification
was observed during follow-up audit session on 27 January 2021. |
|
Water Quality |
30/12/2020 |
Contractor was reminded to clear the debris in
channel. |
Item
was remarked as 210106-R03. Follow-up action is needed to be reviewed. |
06/01/2021 |
Contractor was reminded to clear the debris in
channel. |
Improvement/Rectification
was observed during follow-up audit session on 13 January 2021. |
|
22/01/2021 |
Contractor was reminded to provide sandbag to prevent surface runoff
and waste water discharge into nearby water course. |
Item
was remarked as 210127-R03. Follow-up action is needed to be reviewed. |
|
27/01/2021 |
To prevent surface muddy runoff from entering
nearby planting area. |
Follow-up
action is needed to be reported in the following month. |
|
Waste / Chemical Management |
22/01/2021 |
General refuse should be disposed of properly. |
Improvement/Rectification
was observed during follow-up audit session on 27 January 2021. |
22/01/2021 |
Properly clear the oil spillage from the
generator. |
Item
was remarked as 210127-R02. Follow-up action is needed to be reviewed. |
|
27/01/2021 |
To avoid overlapping of chemical and provide
adequate bund capacity for storage. |
Follow-up
action is needed to be reported in the following month. |
|
27/01/2021 |
Properly clear the oil stain from the air
compressor. |
Follow-up
action is needed to be reported in the following month. |
|
Ecology |
30/12/2020 |
Hoarding was erected at part of active works
area. Hoarding erection is still processing and will be checked and
reviewed. |
Improvement/Rectification
was observed during follow-up audit session on 6 January 2021. |
Contract No.: ND/2019/03 |
|||
Air Quality |
08/01/2021 |
Exposed worksite and haul road should be watered
at least once per hour to avoid dust generation. |
Improvement/Rectification
was observed during follow-up audit session on 15 January 2021. |
08/01/2021 |
NRMM Label was observed faded, Contractor was
reminded to replace the NRMM Label. |
Improvement/Rectification
was observed during follow-up audit session on 15 January 2021. |
|
Waste/ Chemical Management |
08/01/2021 |
General refuse should be disposed of properly. |
Improvement/Rectification
was observed during follow-up audit session on 15 January 2021. |
15/01/2021 |
General refuse should be disposed of regularly. |
Improvement/Rectification
was observed during follow-up audit session on 22 January 2021. |
|
29/01/2021 |
Drip tray should be provided for chemical
storage. |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/05 |
|||
Air Quality |
28/12/2020 |
NRMM label was observed faded. Contractor was
reminded to display valid NRMM label. (Portion 6) |
Improvement/Rectification
was observed during follow-up audit session on 6 January 2021. |
28/12/2020 |
To keep public road near site entrance clean and
free of dust. |
Improvement/Rectification
was observed during follow-up audit session on 6 January 2021. |
|
04/01/2021 |
NRMM label should be displayed on regulated
machines. |
Improvement/Rectification
was observed during follow-up audit session on 13 January 2021. |
|
13/01/2021 |
NRMM label was observed faded. Contractor was
reminded to display valid NRMM label. |
Improvement/Rectification
was observed during follow-up audit session on 18 January 2021. |
|
Water Quality |
25/01/2021 |
Avoid any untreated wastewater/muddy water runoff into nearby
watercourse and site runoff should be directed to sedimentation tank before
discharging. |
Follow-up
action is needed to be reported in the following month. |
25/01/2021 |
Contractor was reminded to regularly monitor the sedimentation tank
to avoid overflow. |
Follow-up
action is needed to be reported in the following month. |
|
Waste / Chemical Management |
28/12/2020 |
To store chemical containers at area with drip
tray provided. (Portion 6) |
Improvement/Rectification
was observed during follow-up audit session on 6 January 2021. |
04/01/2021 |
The chemical waste container should be locked. |
Improvement/Rectification
was observed during follow-up audit session on 13 January 2021. |
|
18/01/2021 |
Drip tray should be provided for chemical
storage. |
Improvement/Rectification
was observed during follow-up audit session on 25 January 2021. |
|
Contract No.: ND/2019/06 |
|||
Air Quality |
11/01/2021 |
To further
enhance dust mitigation measure including watering for works area. |
Improvement/Rectification
was observed during follow-up audit session on 21 January 2021. |
Water Quality |
11/01/2021 |
Contractor
was reminded to clear the mud regularly and prevent/ avoid any muddy water
discharge into nearby watercourse. |
Improvement/Rectification
was observed during follow-up audit session on 21 January 2021. |
Waste / Chemical Management |
06/01/2021 |
Housekeeping should be improved on site. |
Improvement/Rectification
was observed during follow-up audit session on 11 January 2021. |
Ecology |
11/01/2021 |
Dull green site barrier fences should be erected
around all active works areas. |
Improvement/Rectification
was observed during follow-up audit session on 21 January 2021. |