Table 10.1   Summary of Site Audit

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/05

ND/2019/06

Weekly site audit with representative of the Supervisor’s Representative and the Contractor

5th , 12th, 19th, 26th January 2021

6th , 13th, 22nd, 27th January 2021

8th, 15th, 22nd, 29th  January 2021

4th, 13th, 18th, 25th January 2021

6th, 11th, 21st, 28th January 2021

Joint Site Audit with representative of the Supervisor’s Representative, the Contractor and IEC

12th January 2021

22nd January 2021

22nd January 2021

13th January 2021

11th January 2021