12           FUTURE KEY ISSUES

Key Issues in the Coming Two Months

12.1     The major site activities, potential environmental impacts and recommended mitigation measures for the coming two months are shown in Table 12.1.

Table 12.1    Summary Table for Site Activities, Potential Environmental Impacts and Recommended Mitigation Measures in the coming Months

Contract No.

Major Site Activities ( January to February 2022)

Location/ Working Period

Potential Environmental Impact

Recommended Mitigation Measures

ND/2019/01

(a) Site clearance

Portion 1a, 1b, 1e, 2, 3, 5, 6a, 7

- Construction Dust impact

- Noise Impact (Construction Phase)

- Water Quality Impact (Construction Phase)

- Waste Management (Construction Waste)

 

 

Air

-              Watering on exposed earth and haul road.

-              Cover the stockpiles or dusty materials.

-              Deploy water browsers to water the haul road.

-              Deploy mist-cannon on site

-              Install sprinkler system for dust suppression.

-              Provide shelter with top and 3-sides for cement production activities.

-              Entirely cover the Arsenic-containing soil.

-              Store the bulk cement in enclosed silo tank for Solidification / Stabilization treatment.

-              Close the mechanical cover of the vehicles used for transporting dusty materials.

-              Establish vehicle wheel washing facilities at vehicle exit points.

-              Speed control of site vehicles.

-              Erect solid site hoarding.

Noise

-              Regular inspect of construction plants in good condition

-              Provide temporary noise screens if necessary.

-              Use of Quiet plants (QPME) and working methods if possible.

-              Sequencing operation of construction plants where practicable.

-              Shut down the machines and plant if not in use.

-              Only well-maintained plant to be operated on-site.

-              Mobile plant to be sited as far away from NSRs as possible and practicable.

-              Conduct noise monitoring regularly.

-              Erect silent-up noise barrier at Portion 6b.

Water

-              Set up wastewater treatment system (AquaSed) on site.

-              Erect soil bund / temporary drain to divert /collect surface runoff.

-              Maintain the drainage and wastewater treatment facilities.

Waste / Chemical Management

-              Sort out demolition debris and excavated materials from demolition works to recover reusable / recyclable portions.

-              Provide recycling bin on site, encourage reuse and recycle as much as possible.

-              Provide drip tray for chemical containers.

-              Chemical spill kit available on site.

-              Chemical waste cabinet available on site.

-              Chemical wastes to be stored in appropriate containers and collected by a licensed chemical waste collector.

-              Delivery of yard waste to Y-Park for reuse/ upcycling or agreed alternative site.

(b) GI works

Portion 1b, 9b

(c) Excavation

Portion 3, 5, 6a, 7,  8a, 8b, 9b, 9c, 10a, 10b

(d) Construction of retaining wall

Portio6a, 8a

(e) Soil nailing/ grouting

Portion

(f)  Demolition of existing structure

Portion 1a, 1b, 1e, 9b

(g) Construction of temporary site haul road

Portion 2, 5, 6a, 7, 8a, 10a

(h) Operation of HAC treatment facility

Portion 6b

(i)  Tree felling

Portion 1a, 2, 3

(j)  Drainage Works

Portion 1b, 5, 6a, 7, 8a, 9b, 10a, 11b

(k) Sheetpiling

Portion 1b, 5, 6a, 7, 8b, 9b, 10a, 10b

 

 

ND/2019/02

(a)        Hoarding erection

Portion 10

Air, Noise, Waste

-              Dusty works should be spray water or idle stockpile or slop should be covered by Tarpaulin sheet properly.

-              Wheel washing should be carried out at every exit.

-              Plants should be well maintained to prevent dark smoke and oil leakage. Idle plant should be turned off.

-              Drip tray should be provided for all chemical and stationary plants.

-              No construction works shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is obtained.

-              Waste should be sorted and dispose according to the Waste Management Plan

-              No direct discharge of wastewater into storm drains is allowed. Wastewater must be de-silted before discharged in accordance with the water discharge license.

-              Dull green barrier and ecological measures should be implemented according to the Ecological protection plan.

(b)       Tree Felling

Portion 7

Air, Noise, Waste

(c)        Pre-bored Socketed H-pile

Portion 7, 9, 10

Air, Noise, Water, Waste, Ecology

(d)       ELS

Portion 1, 9

Air, Noise, Water, Waste, Ecology

(e)        Construction of Pile Cap

Portion 9

Air, Noise, Water, Waste, Ecology

(f)        Pipe Jacking

Portion 1

Air, Noise, Water, Waste

ND/2019/03

(a)        Excavation of irrigation channel

Long Valley

-     C&D waste

-     Air pollution

-     Noise pollution

-              Watering exposed earth regularly

-              Cover C&D material by tarpaulin

-              Adopt QPME for excavation

(b)       Excavation of trench in Yin Kong Road

Portion 1 and Portion 1A

-     C&D waste

-     Air pollution

-     Noise pollution

-     Water pollution

-              Watering exposed earth regularly

-              Cover C&D material by tarpaulin

-              Noise barrier for screening from source of noise

-              Wastewater will be treated before discharging to channel

(c)        Demolition of existing structure

Long Valley

-     C&D material

-     Air Pollution

 

-              Cover C&D material by tarpaulin

-              Watering while demolish the structure

 

(d)       Construction works of storage shed and Type 2 Storage House

Long Valley

-     C&D material

-     Air Pollution

 

-              Watering exposed earth regularly

-              Cover C&D material by tarpaulin

 

ND/2019/04

(a)        Sheet piling

Portion H, Bridge F, A2

-     Air, Noise, Waste

-              Dusty works should be sprayed with water or stockpile should be covered by tarpaulin properly.

-              Plants should have maintenance to prevent dark smoke and oil leakage. Idle plant should be turned off.

-              Drip tray should be provided for all chemical and stationary plants.

-              No construction works shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is granted.

-              Waste should be sorted and disposed according to Waste Management Plan.

-              No direct discharge of wastewater into storm water drains is allowed. Wastewater must be desilted before discharging according to water discharge license.

(b)       Bored piling

Bridge A1, A2, A3

-     Air, Noise, Water, Waste

(c)        Predrill

Bridge A1, A3, Portion E, H

-     Air, Noise, Water, Waste

(d)       Excavation

Portion H

-     Air, Noise, Waste

(e)        Site clearance

Portion H

-     Air, Noise, Waste

(f)        Tree felling

Portion H

-     Air, Noise, Waste

ND/2019/05

(a)        Pre drilling for bored piles

B1 & B2(Portion II), C1(Portion II) & C1-03

-     Construction Dust Impact

-     Noise Impact

-     Water Quality Impact (Construction Phase)

-     Waste Management  (Construction Waste)

-     Landscape and Visual

-     Cultural Heritage

-              Regular watering on exposed worksites and haul road

-              Stockpiling area should be provided with covers and water spraying system

-              Only well-maintained plant to be operated on-site

-              Plant known to emit noise strongly in one direction, where possible, be orientated so that the noise is directed away from nearby NSRs; 

-              Mobile plant to be sited as far away from NSRs as possible practicable

-              All open stockpiles of construction materials  of more than 50m3 to be covered with tarpaulin

-              Manholes to be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system

-              All vehicles and plant to be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.

-              Segregate and store different types of waste in different containers, skip or stockpiles to enhance reuse or recycling of materials and their proper disposal

-              Sort out demolition debris and excavated materials from demolition works to recover reusable/recyclable portions

-              Provide training to workers on appropriate waste management procedures, including waste reduction, reuse and recycling

-              To adopt other good site practice, such as arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site and regular cleaning and maintenance programme for drainage

-              Chemical wastes to be stored in appropriate containers and collected by a licensed chemical waste Contractor. Chemical wastes (e.g. spent lubricant oil) should be recycled at an appropriate facility as far as possible, while the chemical waste that cannot be recycled should be disposed of at either the Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation

-              Conducting Construction Vibration Monitoring

-              Tree Protection & Preservation – Exiting trees to be retained within the Project site should be carefully protected during construction. In particular OVTs will be preserved according to ETWB Technical Circular (Works) No. 29/2004.

-              Tree Transplantation – Tree unavoidably affected by the Project works should be transplanted where practical. Tree should be transplanted straight to their final receptor site and not held in a temporary nursey as far as possible.

-              Erect 2m high dull green site boundary fence.

(b)       Bored piling

B1(Portion I), B1&B2(Portion II), C1(Portion II), C1 03, C1 04, C2

01, E3 01, C2 02, C2 03a, C2 03b,

C3 02, C3 03a, C3 04a, D2 01, D2

03, E2 01

(c)        ELS & Pile Cap Construction

C3

03b, C3 04b, C4 03, C4 04a, C4

04b, D1 01, D1 02, D1 03, D1 04, E1 01, E1 02, E1 03 & E1 04 , D2 02, E3 03, E2 03

(d)       Footing Construction

C4-02

(e)        Utitilies Diversion Works and Permanent Road Works

Venton Area,

TWSR-West, D2-03

(f)        Pier Construction

C4-03, C4-04a, C4-04b, D1-01, E1-01, E1-02, E1-03, E1-04, C4-01a, C4-01b, E2-02

(g)       Abutment construction

LT1, PO2, AB1

of HKY

(h)       Launching Girder & Form Traveler Fabrication

CTC Storage Yard

(i)         Drainage & Water Mains construction

Portion XI, XIII, XVII, XVIII

(j)         Demolition

Kee Kei area in Portion XVIII

ND/2019/06

A.         Construction of finishing works and E&M works for the Management Office Building (MOB)

Portion 4

-     Noise pollution

-     Water pollution

-              Adopt noise barrier in screening noise

-              Wastewater generated after wheel washing of

vehicles should be treated properly before discharge

B.         Erection of the seam roof and skylight frame of steel canopy

Portion 3

-     Air pollution

-     Noise pollution

-              Adopt “Approved” NRMM Label

-              Adopt noise barrier in screening noise

C.         Construction of concrete carriageway

Portion 3

-     Air pollution

-     Noise pollution

-              Adopt QPME for excavator

-              Washing the truck wheel before leaving the site

D.         Construction of screeding on stall area

Portion 3

-     Noise pollution

-              Adopt noise barrier in screening noise

E.          Construction of underground utilities in the final stage market

Portion 3

-     Noise pollution

-     C&D waste

-     Air pollution

-              Adopt QPME for excavator

-              Cover C&D waste by impervious sheeting

-              Washing the truck wheel before leaving the site

F.          Finishing works and E&M installations for the additional water tank and pump house

Portion3

-     Air pollution

-     Noise pollution

 

-              Unloading materials shall be kept in minimum height and speed

-              Adopt “ Approved” NRMMM\Label

G.         E&M installations for the steel canopy

Portion 3

-     Air pollution

-              Adopt ultra-low Sulphur diesels

ND/2019/07

(a)        Site clearance

Portion 2, 4, 5

-     Construction Dust Impact

-     Noise Impact

-     Water Quality Impact (Construction Phase)

-     Waste Management (Construction Waste)

-     Landscape and Visual

-              Regular watering on exposed worksites and haul road.

-              Stockpiling area should be provided with covers and water s praying system.

-              Only well maintained plant to be operated on site.

-              Plant known to emit noise strongly in one direction, where possible; be orientated so that the noise is directed away from nearby NSRs.

-              Mobile plant to be sited as far away from NSRs as possible practicable.

-              All open stockpiles of construction materials of more than 50m3 to be covered with tarpaulin.

-              Manholes to be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system.

-              All vehicles and plant to be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.

-              Segregate and store different types of waste in different containers, skip or stockpiles to enhance reuse or recycling of materials and their proper disposal.

-              Sort out demolition debris and excavated materials from demolition works to recover reusable/recyclable portions.

-              Provide training to workers on appropriate waste management procedures, including waste reduction, reuse and recycling.

-              To adopt other good site practice, such as arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site and regular cleaning and maintenance programme for drainage.

-              Chemical wastes to be stored in appropriate containers and collected by a licensed chemical waste Contractor. Chemical wastes (e.g. spent lubricant oil) should be recycled at an appropriate facility as far as possible, while the chemical waste that cannot be recycled should be disposed of at either the Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

-              Tree Protection & Preservation – Existing trees to be retained within the Project Site should be carefully protected during construction. In particular OVTs will be preserved according to ETWB Technical Circular (Works) No. 29/2004.

-              Tree Transplantation Trees unavoidably affected by the Project works should be transplanted where practical. Trees should be transplanted straight to their final receptor site and not held in a temporary nursery as far as possible.

-              Erect 2m high dull green site boundary fence.

-              Light Control Construction day and night time lighting should be controlled to minimize glare impact to adjacent VSRs during the Construction phase.

(b)       Erection of site hoarding

Portion 2, 4

(c)        C&D waste disposal

Portion 1, 2, 4, 5

(d)       Ground investigation works

Portion 3, 4

(e)        Construction of box culvert

Portion 2

(f)        Filing works

Portion 1, 2, 4

(g)       Tree felling/ disposal of yard waste

Portion 2, 4, 5

(h)       Construction of site haul road

Portion 1, 4

(i)         Sewage works

Portion 1, 3

(j)         Demolition of villager’s houses

Portion 4, 5

(k)       Drainage Works

Portion 1, 3

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12.2     The major site activities in coming two months is shown in Table IV.

Monitoring Schedule for the Next Month

12.3     The tentative environmental monitoring schedule for next month is shown in Appendix D.

Construction Programme for the Next Month

12.4     A tentative construction programme is provided in Appendix A.