10.1
Site
audits were carried out by ET on weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. The
summaries of site audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audit
Environmental Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative of the Supervisor’s
Representative and the Contractor |
7, 14, 21 and 28 Dec 21 |
1, 8, 17, 22 and 29
Dec 21 |
3, 10, 14, 24 and 31
Dec 21 |
2, 10, 16, 23 and 30
Dec 21 |
8, 13, 20 and 28 Dec
21 |
2, 9, 13, 23 and 30
Dec 21 |
3, 9, 17, 24 and 31
Dec 21 |
Joint Site Audit with representative of the Supervisor’s
Representative, the Contractor and IEC |
14 Dec 21 |
17 Dec
21 |
14 Dec
21 |
16 Dec 21 |
8 Dec 21 |
13 Dec 21 |
9 Dec 21 |
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table 10.2.
Table 10.2 Observations and Recommendations during
Site Audits
|
Date |
Observations
and Recommendations |
Follow-up |
Contract No.: ND/2019/01 |
|||
Air Quality |
14/12/2021 |
Dusty stockpile should be covered by imperious
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 21 December 2021. |
Ecology |
14/12/2021 |
Solid dull green barrier should be enhanced along
river channel. |
Improvement/Rectification
was observed during follow-up audit session on 21 December 2021. |
Waste/ Chemical Management |
28/12/2021 |
Drip tray should be provided for chemical
storage. |
Follow-up
action is needed to be reported in the following month. |
Contract No.: ND/2019/02 |
|||
Air Quality |
24/11/2021 |
NRMM Label was observed faded. Contractor was reminded to replace the
NRMM Label. |
Improvement/Rectification
was observed during follow-up audit session on 1 December 2021. |
8/12/2021 |
Replace faded NRMM label on generator. (North Bridge) |
Item
was remarked as 211217-R02. Follow-up action is needed to be reviewed. |
|
17/12/2021 |
Replace faded NRMM label on generator. (North Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 22 December 2021. |
|
Water Quality |
1/12/2021 |
Dusty slope surface should be covered. (North Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 8 December 2021. |
1/12/2021 |
Remove dusty materials beside the U-channel and clear the stagnant
water inside the U-channel. (South Bridge) |
Item
was remarked as 211208-R01. Follow-up action is needed to be reviewed. |
|
1/12/2021 |
To enhance water control measure to prevent any discharge of muddy
water to Sheung Yue River. (河口) |
Item
was remarked as 211208-O04. Follow-up action is needed to be reviewed. |
|
8/12/2021 |
Remove dusty materials beside the U-channel and clear the stagnant
water inside the U-channel. (South Bridge) |
Item
was remarked as 211217-R01. Follow-up action is needed to be reviewed. |
|
8/12/2021 |
To enhance water control measure to prevent any discharge of muddy
water to Sheung Yue River. (河口) |
Item
was remarked as 211217-O03. Follow-up action is needed to be reviewed. |
|
8/12/2021 |
To clear oil leakage from generator on site. (North Bridge) |
Improvement/Rectification
was observed during follow-up audit session on 17 December 2021. |
|
17/12/2021 |
Remove dusty materials beside the U-channel and clear the stagnant
water inside the U-channel. (South Bridge) |
Item
was remarked as 211222-R01. Follow-up action is needed to be reviewed. |
|
17/12/2021 |
To enhance water control measure to prevent any discharge of muddy
water to Sheung Yue River. (河口) |
Item
was remarked as 211222-O02. Follow-up action is needed to be reviewed. |
|
22/12/2021 |
Remove dusty materials beside the U-channel and clear the stagnant
water inside the U-channel. (South Bridge) |
Item
was remarked as 211229-R01. Follow-up action is needed to be reviewed. |
|
22/12/2021 |
To enhance water control measure to prevent any discharge of muddy
water to Sheung Yue River. (河口) |
Item
was remarked as 211222-O02. Follow-up action is needed to be reviewed. |
|
22/12/2021 |
To enhance water control measure to prevent any discharge of muddy water
to Sheung Yue River. (North Bridge) |
Item
was remarked as 211222-O03. Follow-up action is needed to be reviewed. |
|
29/12/2021 |
Remove dusty materials beside the U-channel and clear the stagnant
water inside the U-channel. (South Bridge) |
Follow-up
action is needed to be reported in the following month. |
|
29/12/2021 |
To enhance water control measure to prevent any discharge of muddy
water to Sheung Yue River. (河口) |
Follow-up
action is needed to be reported in the following month. |
|
29/12/2021 |
To enhance water control measure to prevent any discharge of muddy water
to Sheung Yue River. (North Bridge) |
Follow-up
action is needed to be reported in the following month. |
|
29/12/2021 |
Clear and treat the stagnant muddy water inside the U-Channel with
desilting facilities before discharge. (North Bridge) |
Follow-up
action is needed to be reported in the following month. |
|
Contract No.: ND/2019/03 |
|||
Air Quality |
3/12/2021 |
Dusty haul road should be sprayed with water
regularly. |
Improvement/Rectification
was observed during follow-up audit session on 10 December 2021. |
10/12/2021 |
Dusty stockpile should be covered by imperious sheeting. |
Item
was remarked as 211214-R02. Follow-up action is needed to be reviewed. |
|
14/12/2021 |
Exposed worksite and haul road should be watered regularly. |
Improvement/Rectification
was observed during follow-up audit session on 24 December 2021. |
|
14/12/2021 |
Excavated or stockpile of dusty materials should
be covered by impervious sheeting or sprayed with water. |
Improvement/Rectification
was observed during follow-up audit session on 24 December 2021. |
|
24/12/2021 |
Any portion of road leading to construction site
within 30m of a vehicle exit should be kept free from dust and mud. Mud was
observed along portion of road next to Sheung Yue River. |
Improvement/Rectification
was observed during follow-up audit session on 31 December 2021. |
|
Water Quality |
14/12/2021 |
To clean wheel-washing bay regularly. |
Item
was remarked as 211224-R01. Follow-up action is needed to be reviewed. |
24/12/2021 |
To clean wheel-washing bay regularly. |
Item
was remarked as 211231-R01. Follow-up action is needed to be reviewed. |
|
24/12/2021 |
To provide adequate wheel-washing bay facilities
at every vehicle exit so as to prevent vehicles
leaving site with earth mud. |
Improvement/Rectification
was observed during follow-up audit session on 31 December 2021. |
|
31/12/2021 |
To clean wheel-washing bay regularly. |
Follow-up
action is needed to be reported in the following month. |
|
Waste/ Chemical Management |
23/11/2021 |
Empty chemical container should be stored
properly in designated area. |
Item
was remarked as 211203-R02. Follow-up action is needed to be reviewed. |
3/12/2021 |
Empty chemical container should be stored
properly in designated area. |
Improvement/Rectification
was observed during follow-up audit session on 10 December 2021. |
|
14/12/2021 |
Empty chemical containers should be stored at designated
areas. |
Improvement/Rectification
was observed during follow-up audit session on 24 December 2021. |
|
Contract No.: ND/2019/04 |
|||
Air Quality |
2/12/2021 |
Dusty stockpile should be covered by imperious sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 10 December 2021. |
Noise |
2/12/2021 |
To enhance noise mitigation measures along Shek Wu San Tsuen. |
Item
was remarked as 211210-R01. Follow-up action is needed to be reviewed. |
|
10/12/2021 |
To enhance noise mitigation measures along Shek Wu San Tsuen. |
Item
was remarked as 211216-R01. Follow-up action is needed to be reviewed. |
|
16/12/2021 |
To enhance noise mitigation measures along Shek Wu San Tsuen. |
Item
was remarked as 211223-R01. Follow-up action is needed to be reviewed. |
|
23/12/2021 |
To enhance noise mitigation measures along Shek Wu San Tsuen. |
Item
was remarked as 211230-R01. Follow-up action is needed to be reviewed. |
|
30/12/2021 |
To enhance noise mitigation measures along Shek Wu San Tsuen. |
Follow-up
action is needed to be reported in the following month. |
Ecology |
2/12/2021 |
To provide 10m buffer zone along Siu Hang San
Tsuen Stream. |
Item
was remarked as 211210-R02. Follow-up action is needed to be reviewed. |
|
10/12/2021 |
To provide 10m buffer zone along Siu Hang San
Tsuen Stream. |
Item
was remarked as 211216-R02. Follow-up action is needed to be reviewed. |
|
16/12/2021 |
To provide 10m buffer zone along Siu Hang San
Tsuen Stream. |
Item
was remarked as 211223-R02. Follow-up action is needed to be reviewed. |
|
23/12/2021 |
To provide 10m buffer zone along Siu Hang San
Tsuen Stream. |
Improvement/Rectification
was observed during follow-up audit session on 30 December 2021. |
Water Quality |
30/12/2021 |
To ensure sediment in U-channel was cleared
regularly and avoid accumulation. |
Follow-up
action is needed to be reported in the following month. |
Contract No.: ND/2019/05 |
|||
Air Quality |
29/11/2021 |
Dusty stockpile should be covered by imperious
sheeting. |
Improvement/Rectification
was observed during follow-up audit session on 8 December 2021. |
8/12/2021 |
Faded NRMM label shall be replaced. |
Improvement/Rectification
was observed during follow-up audit session on 13 December 2021. |
|
20/12/2021 |
Display valid NRMM label on regulated machine. |
Improvement/Rectification
was observed during follow-up audit session on 28 December 2021. |
|
Water Quality |
8/12/2021 |
Enhance mitigation measures to prevent surface
runoff to Ma Wat River. |
Improvement/Rectification
was observed during follow-up audit session on 13 December 2021. |
13/12/2021 |
Enhance mitigation measures to prevent surface
runoff to Ma Wat River. |
Improvement/Rectification
was observed during follow-up audit session on 20 December 2021. |
|
28/12/2021 |
Enhance mitigation measures to prevent surface
runoff to Ma Wat River. |
Follow-up
action is needed to be reported in the following month. |
|
Waste / Chemical Management |
29/11/2021 |
Remove dusty materials beside the U-Channel and
enhance mitigation measure to prevent muddy water runoff to the U-Channel. |
Improvement/Rectification
was observed during follow-up audit session on 8 December 2021. |
20/12/2021 |
C&D materials should be segregated from other
waste. |
Improvement/Rectification
was observed during follow-up audit session on 28 December 2021. |
|
Contract No.: ND/2019/06 |
|||
Waste / Chemical Management |
2/12/2021 |
General refuse should be disposed of regularly to
avoid accumulation. |
Improvement/Rectification
was observed during follow-up audit session on 9 December 2021. |
Contract No.: ND/2019/07 |
|||
-- |
-- |
-- |
-- |
10.3
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EP to mitigate
environmental impacts in the reporting month are presented in Table 10.3.
Table 10.3 Photographic Records and Implementation
Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013 |
2.9 |
To
minimise adverse impacts on habitats of ecological imprtance in the vicinity of the Project, 2m high solid
dull green site barrier fences shall be erected around all active works areas.(Figure 12) |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 14) |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 15) |
^[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure 16) |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas.(Figure
17) |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance of mitigation measure · Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
[1]: Barrier fences might be subjected to
change according to phasing plan designed at detailed design stage
10.4
Under
EP-467/2013/A (Condition 2.9), to minimise adverse
impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. As the Works programme under above EPs
were still under preparation work and the
barrier fences erection was still progressing in the Reporting Month, 2m high
solid dull green site barrier fences will be checked once in place. The
Hoarding Plan of the above EPs is shown in Figure
13.
10.5
According
to the EIA Report and the Updated EM&A Manual, the Air quality and Noise
mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. Air quality and Noise mitigation measures
implemented by the contractors were closely monitored to prevent water
pollution, especially during dry season. An updated summary of the
Environmental Mitigation Implementation Schedule is provided in Appendix Q. Specific Air quality and
Noise mitigation measures for major construction works in the reporting month are
presented in Table 10.4.
Table 10.4 Specific Air Quality and Noise Mitigation Measures for Major
Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Covering dusty
stockpile |
ND/2019/02 |
Hard paved exposed
haul road |
Hoarding not less than 2.4m tall |
ND/2019/03 |
Deployment of noise
barriers between construction site and NSRs |
Regulated machines
display with Non-road Mobile Machinery labels |
ND/2019/04 |
Access road watered regularly |
Dusty haul road watered regularly |
ND/2019/05 |
Covering dusty
stockpile |
Deployment of noise
barriers between construction site and NSRs |
ND/2019/06 |
Grasscrete for slope protection |
Hard paved exposed haul road |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
Vehicle washing facilities at exit point |
10.6
Waste generated
from Contract No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06
and ND/2019/07 include inert construction and demolition (C&D) materials
and non-inert C&D wastes in the Reporting Month.
10.7
The amount of wastes generated by the construction works of the Contract
No. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05, ND/2019/06 and
ND/2019/07 during the
reporting month are shown in Appendix R.
10.8
The
Contractors are advised to minimize the wastes generated through recycling or
reusing. All mitigation measures stipulated in the Updated EM&A Manual and
waste management plans shall be fully implemented. The status of implementation
of waste management and reduction measures are summited in Appendix Q.
10.9
From
the findings of EIA Report, the area of Long Valley has been assessed as of
high to very high ecological value and is the largest contiguous area of
freshwater wetland habitats in Hong Kong. To safeguard the ecological value of
Long Valley, about 37 hectares of land in Long Valley has been proposed to
develop into Long Valley Nature Park (LVNP) for conserving and enhancing the
ecologically important environment as well as for compensation of the wetland
loss due to the NDA development.
10.10
LVNP is developed according to approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. The
HCMP provides a framework and specifications for development and management of
the LVNP and guides the development to maintain and enhance the 37ha of
low-lying wetland habitats.
10.11
Regarding
to the design, the zoning of land use in the LVNP is intended to maintain the
existing mosaic pattern of wet and dry agriculture, while controlling the
activities that could potentially disturb target habitats and species. The LVNP
will divide into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.12
The
construction of the LVNP started in late 2019 and is expected to be completed
in 2023. During construction period, the progress of construction and wetland
enhancement works are under observation by different stakeholders including
AFCD and green groups. Close communication between AFCD and CEDD are conducted
to exchange views on conservation, restoration and
management of habitats as well as on the planning and design of the park. Also,
advices from green groups, Hong Kong Bird Watching Society (HKBWS) and The
Conservancy Association (CA), are taken on habitat management of Long Valley
and potential effects on habitat and wildlife of each individual work conducted
in Long Valley. Regular meeting are held monthly on 15th
December 2021 in the reporting month to share the progress of LVNP with
different stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC
and farmers.
10.13 Proposals on wetland creation and
restoration, dry agricultural land creation, pond creation, water treatment
wetland and design of irrigation channel are submitted by the Contractor to
achieve the objectives stated in HCMP and accepted by the Engineer with consent
from AFCD before implementation. The Contractor will consult with the
stakeholders for recommendations and suggestions on mitigation measures to minimise the environmental impacts arising from
construction works. The progress of works will be arranged to minimise impacts to avifauna and maintain the habitat for
avifauna. The photographic records of site activities in LVNP are presented in Table 10.5.
Table 10.5 Photographic
Records of Site Activities in LVNP
Agricultural practice are
continued in existing farmland to maintain habitats in Long Valley |
|||
Lotus
pond |
Open
water Habitat |
Chinese
arrowhead pond |
|
Creation of wetland with designated
habitat for biodiversity conservation |
|||
Planting of paddy rice to provide
foraging ground for Yellow-breasted Bunting |
|||
Retention of washing bay for amphibians
breeding |
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
||
Provision of bird island (hidden area) |
Restoring of water flea pond to provide
food source to water birds |
||
Construction of storage sheds for farmers |
an Emberiza lathami was
recorded |
||
Provision of wastewater treatment
facilities |
Provision of noise barrier for noisy
works in Long Valley |
||