Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (January 2022 and February 2022)

ND/2019/01

 

(a)          Site Clearance, remove of existing structures and tree felling in Portion 1a

(b)         Site clearance, ground investigation, sheet piling, excavation and drainage in Portion 1b

(c)          Site Clearance and remove of existing structures in Portion 1e

(d)         Site clearance, tree felling and temporary road construction in Portion 2

(e)          Site clearance, backfilling, excavation and tree felling in Portion 3

(f)          Site clearance, sheet piling and excavation, drainage works and temporary road construction in Portion 5

(g)         Site Clearance, sheet piling and excavation, pipes laying, backfilling, construction of KB01 retaining wall, haul road construction in Portion 6a

(h)         Operation of HAC treatment facility in Portion 6b

(i)           Site clearance, sheetpiling and excavation, pipes laying and construction of APLR in Portion 7

(j)           Construction of retaining Wall, slope cutting, soil nailing, slope drainage and maintenance access construction, RC construction of flushing water service reservoir and fresh water reservoir, construction of temporary haul road in Portion 8a

(k)         Sheet piling for receiving pit, trenchless works, excavation in Portion 8b

(l)           Sheet piling and excavation, pipes laying, demolition of existing structures, GI works in Portion 9b

(m)       Stockpile of soil and excavation in Portion 9c

(n)         Excavation, sheetpiling for ELS, drainage works and road construction in Portion 10a

(o)         Sheetpiling and excavation, drainage works in Portion 10b

(p)         Construction of MBR at 11b

(q)         Construction of temporary sewage pumping station in Portion 14

ND/2019/02

(a)          Pre-bored Socketed H-pile

(b)         Tree felling

(c)          ELS

(d)         Hoarding erection

(e)          Pipe Jacking

(f)          Construction of Pile Cap

ND/2019/03

 

(a)        Portion 1 & Portion 1A

-            Drainage works at Yin Kong Road

(b)       Long Valley

-          Erection of Permanent Boundary Structure

-          Construction of Compacted Earth Bund / Walkway

-          Construction of Ditches

-          Construction of Irrigation Channel

-          Construction of Decking & Sluices

-          Construction of Type 1 Storage House

-          Construction of Type 2 Storage House

-          Construction of Tea House

-          Construction of Composting Facility

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Construction of Storage Sheds

-          Wetland Creation & Restoration works

ND/2019/04

 

(a)           Site clearance

(b)           Tree felling

(c)           Predrill

(d)           Bored piling

(e)           Excavation

(f)            Sheet piling

(g)           ELS

ND/2019/05

(a)           North Team Works

-          Pre-drilling for bored piles at B1 & B2(Portion II), C1(Portion II) & C1-03

-          Bored piling at B1(Portion I), B1&B2(Portion II), C1(Portion II), C1-03, C1-04, C2-01, C2-02, C2-03a, C2-03b, C3-02, C3-03a, C3-04a, D2-01, E2-01

-          ELS and Pile cap construction at C3-03b, C3-04b, C4-03, C4-04a, C4-04b, D1-01, D1-02, D1-03, D1-04, E1-01, E1-02, E1-03 & E1-04

-          Footing construction at C4-02.

-          Pier Construction at C4-03, C4-04a, C4-04b, D1-01, E1-01, E1-02, E1-03, E1-04

(b)          Viaduct Works

-          Installation of the 4th to 5th typical segment mould and SOP mould

-          Fabrication of 6th to 8th typical segment mould to be completed by the end of Feb 2022

-          1st and 2nd SOP

-          Target to cast in12 segments in and 16 segments

-          Fabrication of launching girder (LG) is in progress

-          Fabrication of 1st set Form Travel (FT)

-          Fabrication of pier bracket of Pier C4-04M

-          Complete ground beams of segment motorized trolley in CTC yard

(c)           South Team Works

-          Venton Area – Gas main laying, 11kv and 132kv cross road duct laying

-          Portion 13 –132kv duct laying. DN1200 storm drain construction

-          Portion 17 and 18 – Construction of DN 1650 storm. DN 600 and DN450 sewer

-          Portion 18 – 132kv duct laying, Gas main laying

-          Kee Kei area – demolish boundary wall

-          TWSR (West) – RW06 construction

-          HKY FB (East) – construction of LT1, P02

-          Portion 11 – DN1200 and DN600 watermain laying work

-          E2-02 pier – construction of tower crane foundation

-          E2-03 – Pile cap construction

-          E3-01 – Pile cap construction

-          E3-03 – Pier construction

-          D2-02 – Pile cap construction.

-          D2-03 – Temp. drainage diversion, access tower erection, temp. lighting, Piling works

ND/2019/06

 

(a)          Finishing works for the Management Office Building (MOB) at Portion 4.

(b)         Rectification works for T&C of E&M installations for the steel canopy, MOB and additional water tank and pump house at Portion 3

(c)          Construction of concrete carriageway at Portion 3

(d)         Construction of screeding on stall area at Portion 3

(e)          Construction of footings of additional covered walkway at Portion 3

(f)          Finishing works for the additional water tank and pump house at Portion 3

ND/2019/07

(a)        Site clearance at Portion 4 and 5

(b)        Erection of site hoarding at Portion 4

(c)        C&D waste disposal at Portion 1, 2, 4 and 5

(d)        G.I. works at Portion 4 and 5

(e)        Construction of box culvert at Portion 2

(f)         Filling works at Portion 1, 2 and 4

(g)        Tree felling/ Disposal of yard waste at Portion 4

(h)        Construction of site haul road at Portion 4

(i)         Demolition of villagers houses at Portion 4 and 5

(j)         Drainage works and sewage works at Portion 1, 3 and 4

(k)        Main piling works and Portion 5