Table IV Summary
Table for Site Activities in the coming Two Months
Contract No. |
Site Activities (January 2022 and February 2022) |
ND/2019/01 |
(a)
Site Clearance, remove of existing structures and tree felling in
Portion 1a (b)
Site clearance, ground investigation, sheet piling, excavation
and drainage in Portion 1b (c)
Site Clearance and remove of existing structures in Portion 1e (d)
Site clearance, tree felling and temporary road construction in
Portion 2 (e)
Site clearance, backfilling, excavation and tree felling in Portion 3 (f)
Site clearance, sheet piling and excavation, drainage works and
temporary road construction in
Portion 5 (g)
Site
Clearance, sheet piling and excavation, pipes laying, backfilling,
construction of KB01 retaining wall, haul road construction in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Site
clearance, sheetpiling and excavation, pipes laying and construction of APLR in
Portion 7 (j)
Construction
of retaining Wall, slope cutting, soil nailing, slope drainage and
maintenance access construction, RC construction of flushing water service
reservoir and fresh water reservoir, construction of temporary haul road in
Portion 8a (k)
Sheet
piling for receiving pit, trenchless works, excavation in Portion 8b (l)
Sheet piling and excavation, pipes laying,
demolition of existing structures, GI works in Portion 9b (m)
Stockpile
of soil and excavation in Portion 9c (n)
Excavation,
sheetpiling for ELS, drainage works and road construction in Portion 10a (o)
Sheetpiling
and excavation, drainage works in Portion 10b (p)
Construction of MBR at 11b (q)
Construction of temporary sewage pumping station in Portion 14 |
ND/2019/02 |
(a)
Pre-bored
Socketed H-pile (b)
Tree
felling (c)
ELS (d)
Hoarding
erection (e)
Pipe
Jacking (f)
Construction
of Pile Cap |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Drainage
works at Yin Kong Road (b) Long Valley -
Erection
of Permanent Boundary Structure -
Construction
of Compacted Earth Bund / Walkway -
Construction
of Ditches -
Construction
of Irrigation Channel -
Construction
of Decking & Sluices -
Construction
of Type 1 Storage House -
Construction
of Type 2 Storage House -
Construction
of Tea House -
Construction
of Composting Facility -
Construction
of Bird Hide -
Construction
of Outdoor Classroom -
Construction
of Storage Sheds -
Wetland
Creation & Restoration works |
ND/2019/04 |
(a)
Site clearance (b)
Tree felling (c)
Predrill (d)
Bored piling (e)
Excavation (f)
Sheet piling (g)
ELS |
ND/2019/05 |
(a)
North Team Works -
Pre-drilling for bored piles at B1 &
B2(Portion II), C1(Portion II) & C1-03 -
Bored piling at B1(Portion I), B1&B2(Portion
II), C1(Portion II), C1-03, C1-04, C2-01, C2-02, C2-03a, C2-03b, C3-02,
C3-03a, C3-04a, D2-01, E2-01 -
ELS and Pile cap construction at C3-03b, C3-04b,
C4-03, C4-04a, C4-04b, D1-01, D1-02, D1-03, D1-04, E1-01, E1-02, E1-03 &
E1-04 -
Footing construction at C4-02. -
Pier Construction at C4-03, C4-04a, C4-04b,
D1-01, E1-01, E1-02, E1-03, E1-04 (b)
Viaduct Works -
Installation of the 4th to 5th typical segment
mould and SOP mould -
Fabrication of 6th to 8th typical segment mould
to be completed by the end of Feb 2022 -
1st and 2nd SOP -
Target to cast in12 segments in and 16 segments -
Fabrication of launching girder (LG) is in
progress -
Fabrication of 1st set Form Travel (FT) -
Fabrication of pier bracket of Pier C4-04M -
Complete ground beams of segment motorized
trolley in CTC yard (c)
South Team Works -
Venton Area – Gas main laying, 11kv and 132kv
cross road duct laying -
Portion 13 –132kv duct laying. DN1200 storm drain
construction -
Portion 17 and 18 – Construction of DN 1650
storm. DN 600 and DN450 sewer -
Portion 18 – 132kv duct laying, Gas main laying -
Kee Kei area – demolish boundary wall -
TWSR (West) – RW06 construction -
HKY FB (East) – construction of LT1, P02 -
Portion 11 – DN1200 and DN600 watermain laying
work -
E2-02 pier – construction of tower crane
foundation -
E2-03 – Pile cap construction -
E3-01 – Pile cap construction -
E3-03 – Pier construction -
D2-02 – Pile cap construction. -
D2-03 – Temp. drainage diversion, access tower
erection, temp. lighting, Piling works |
ND/2019/06 |
(a)
Finishing works for the Management Office Building (MOB) at
Portion 4. (b)
Rectification works for T&C of E&M installations for the
steel canopy, MOB and additional water tank and pump house at Portion 3 (c)
Construction of concrete carriageway at Portion 3 (d)
Construction of screeding on stall area at Portion 3 (e)
Construction of footings of additional covered walkway at Portion
3 (f)
Finishing works for the additional water tank and pump house at
Portion 3 |
ND/2019/07 |
(a)
Site clearance at Portion 4 and 5 (b)
Erection of site hoarding at Portion 4 (c)
C&D waste disposal at Portion 1, 2, 4 and 5 (d)
G.I. works at Portion 4 and 5 (e)
Construction of box culvert at Portion 2 (f)
Filling works at Portion 1, 2 and 4 (g)
Tree felling/ Disposal of yard waste at Portion 4 (h)
Construction of site haul road at Portion 4 (i)
Demolition of villager’s houses at Portion 4 and 5 (j)
Drainage works and sewage works at Portion 1, 3
and 4 (k)
Main piling works and Portion 5 |