EXECUTIVE SUMMARY

Introduction

1.      This is the 26th monthly Environmental Monitoring and Audit (EM&A) Report under First Phase Development of Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs), comprising the Advance Works and First Stage Works (the Project). This report was prepared by Wellab Limited under “Service Contract No. NDO 04/2019 Environmental Team for Environmental Monitoring and Audit Works in Construction Phase for the First Phase Development of KTN and FLN NDAs” (hereinafter called the “Service Contract”). This report documents the findings of Environmental Monitoring and Audit (EM&A) work conducted in December 2021.

 

2.      During the reporting month, the following Works Contracts under relevant Environmental Permit(s) were undertaken for the Project:

 

Table I                Works Contracts under relevant Environmental Permit(s) in the Reporting Month

Works Contracts

Environmental Permit No.

Designated Project (DP)

Commencement date of construction

Contract No. ND/2019/01 - Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works

EP-466/2013

Castle Peak Road Diversion

12th August 2020

EP-467/2013/A

Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement

12th August 2020

EP-468/2013/A

Kwu Tung North New Development Area Road D1 to D5

1st June 2020

EP-470/2013

Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works

23rd March 2020

Contract No. ND/2019/02 - Kwu Tung North New Development Area, Phase 1: Roads and Drains between Kwu Tung North New Development Area and Shek Wu Hui

EP-469/2013

Sewage Pumping Stations in Kwu Tung North New Development Area

28th October 2020

Contract No. ND/2019/03 - Kwu Tung North New Development Area, Phase 1: Development of Long Valley Nature Park

EP-468/2013/A

Kwu Tung North New Development Area Road D1 to D5

3rd July 2020

EP-473/2013/A

Fanling Bypass Eastern Section (New Road)

6th October 2020

Contract No. ND/2019/04 –

Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shek Wu San Tsuen North to Lung Yeuk Tau)

EP-473/2013/A

 

Fanling Bypass Eastern Section (New Road)

23rd February 2021

EP-546/2017

Fanling North Temporary Sewage Pumping Station

16th February 2021

Contract No. ND/2019/05 -

Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shung Him Tong to Kau Lung Hang)

EP-473/2013/A

Fanling Bypass Eastern Section (New Road)

1st August 2020

Contract No. ND/2019/06 - Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

EP-475/2013/A

Reprovision of temporary Wholesale Market in Fanling North New Development Area

29th October 2019

Contract No. ND/2019/07 –

Fanling North New Development Area, Phase 1: Site Formation and Infrastructure Works

Works area not under relevant Environmental Permit for Phase 1 of the Project.

1st March 2021

Environmental Monitoring and Audit Progress

3.      A summary of the EM&A activities in this reporting month is listed in Table II below:


 


Table II        Summary Table for EM&A Activities in the Reporting Month

EM&A Activities

Monitoring Station (s)

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/04

ND/2019/05

ND/2019/06

ND/2019/07

1-hr Total Suspended Particulates (TSP) Monitoring

FLN-DMS1

N/A

N/A

2, 8, 14, 20, 24 and 30 Dec 21

2, 8, 14, 20, 24 and 30 Dec 21

N/A

N/A

N/A

FLN-DMS3

N/A

N/A

2, 8, 14, 20, 24 and 30 Dec 21

FLN-DMS5

1, 7, 13, 17, 23 and 29 Dec 21

1, 7, 13, 17, 23 and 29 Dec 21

N/A

KTN-DMS4

1, 7, 13, 17, 23 and 29 Dec 21

1, 7, 13, 17, 23 and 29 Dec 21

N/A

24-hr TSP Monitoring

FLN-DMS1

N/A

N/A

1, 7, 13, 17, 23 and 29 Dec 21

1, 7, 13, 17, 23 and 29 Dec 21

N/A

N/A

N/A

FLN-DMS3

N/A

N/A

1, 7, 13, 17, 23 and 29 Dec 21

FLN-DMS5A

17, 23 and 29 Dec 21

17, 23 and 29 Dec 21

N/A

KTN-DMS4

1, 7, 13, 17, 23 and 29 Dec 21

1, 7, 13, 17, 23 and 29 Dec 21

N/A

Noise Monitoring

CP-FLN-NMS1

N/A

2, 8, 14, 24 and 30 Dec 21

N/A

CP-FLN-NMS2

N/A

2, 8, 14, 24 and 30 Dec 21

N/A

CP-KTN-NMS2

1, 7, 13, 23 and 29 Dec 21

N/A

N/A

CP-KTN-NMS3

CP-KTN-NMS5

CP-KTN-NMS6

N/A

1, 7, 13, 23 and 29 Dec 21

Ecological Survey

Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley

N/A*

N/A*

2, 3, 8, 9, 16, 23, 24, 28 and 29 Dec 21

2, 8, 16, 23 and 28 Dec 21

N/A*

N/A*

N/A*

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream

N/A*

N/A*

N/A*

N/A*

N/A*

N/A*

N/A*

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

10 and 15 Dec 21

10 and 15 Dec 21

10 Dec 21

10 Dec 21

10 Dec 21

N/A*

N/A*

24-hr RSP (Ambient Arsenic) Monitoring for Land Contamination

6, 10, 16, 22 and 28 Dec 21

N/A

6, 10, 16, 22 and 28 Dec 21

N/A

N/A

N/A

N/A

Water Quality Monitoring

N/A

1, 3, 6, 8, 10, 13, 15, 17, 20, 22, 24, 27, 29 and 31 Dec 21

N/A

1, 3, 6, 8, 10, 13, 15, 17, 20, 22, 24, 27, 29 and 31 Dec 21

N/A

N/A

N/A

Landfill Gas Monitoring

31 Dec 21

N/A

N/A

N/A

N/A

N/A

N/A

Built Heritage Monitoring

N/A

N/A

N/A

N/A

Daily assessment subject to construction works conducted within assessment area

N/A

N/A

Environmental Site Inspection

7, 14, 21 and 28 Dec 21

1, 8, 17, 22 and 29 Dec 21

3, 10, 14, 24 and 31 Dec 21

2, 10, 16, 23 and 30 Dec 21

8, 13, 20 and 28 Dec 21

2, 9, 13, 23 and 30 Dec 21

3, 9, 17, 24 and 31 Dec 21

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remark:

N/A – No relevant monitoring is required according to updated EM&A Manual

N/A* – No relevant monitoring is required according to Baseline Ecological Monitoring Plan (Table 3.1)

[1] Since the distance between monitoring station CP-KTN-NMS2 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03

[2] Since the distance between monitoring station CP-KTN-NMS3 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03

[3] Since the distance between monitoring station CP-KTN-NMS1 and site boundary of ND/2019/02 under EP-469/2013 exceeds 300m. The monitoring station is not applicable to ND/2019/02

[4] Since the distance between monitoring station FLN-DMS1 and site boundary of ND/2019/05 under EP-473/2013/A exceeds500m. The monitoring station is not applicable to ND/2019/05

[5] Since the distance between monitoring station FLN-DMS3 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 500m. The monitoring station is not applicable to ND/2019/03 and ND/2019/04

[6] Since the distance between monitoring station FLN-DMS5 and site boundary of ND/2019/05 under EP-473/2013/A exceeds 500m. The monitoring station is not applicable to ND/2019/05

[7] Since the distance between monitoring station CP-FLN-NMS2 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03 and ND/2019/04.

[8] Since the distance between monitoring station CP-FLN-NMS1 and site boundary of ND/2019/03 under EP-473/2013/A exceeds 300m. The monitoring station is not applicable to ND/2019/03.

[9] 24-hr TSP monitoring at FLN-DMS5 – Noble Hill was suspended since 19 Nov 2021 as the set up has been reported stolen on 19 Nov 2021. The proposal of alternative station FLN-DMS5A has been approved and operated since 17 Dec 2021.


 


Breaches of Action and Limit Levels

 

4.      Summary of the environmental exceedances of the reporting month is tabulated in Table III.

 

Table III   Summary Table for Events Recorded in the Reporting Month

Environmental Monitoring

Parameter

No. of non-project related Exceedances

Total No. of non-project related Exceedances

No. of Exceedance related to the Construction Works of the Contract

Total No. of Exceedance related to the Construction Works of the Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

0

0

24-hr TSP

0

0

0

0

0

0

24-hr RSP

(Ambient Arsenic)

0

0

0

0

0

0

Noise

Leq(30min)

0

0

0

0

0

0

Water Quality [1]

DO

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

SS

0

0

0

0

0

0

Arsenic

0

0

0

0

0

0

Landfill Gas

O2

0

0

0

0

0

0

CH4

CO2

Cultural heritage

Built Heritage Monitoring

0

0

0

0

0

0

 

Air Quality

 

5.      All construction air quality monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Construction Noise

6.      All construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

Water Quality

 

7.      All additional water quality monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

 

8.      No construction of channel for alternation of natural streams was carried out in the reporting month. Therefore, no water quality monitoring according to pre-construction ET’s Updated EM&A Manual and Baseline Water Quality Monitoring Report (KTN & FLN NDA) was conducted. For the details, please refer to Section 5.

Land Contamination

9.      All ambient arsenic monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.

Landfill Gas Monitoring

10.  Monitoring of landfill gases in the reporting month was carried out by the Contractor under ND/2019/01 at excavation location, Portion 6b. No Limit Level exceedance was recorded.

Built Heritage Monitoring

11.  Built heritage monitoring in the reporting month was carried out by the Contractor under ND/2019/05 for surveyed cultural heritage. No Limit Level exceedance was recorded.

 

Ecological Monitoring

12.  All ecological monitoring was conducted as scheduled in the reporting month. Action and limit level will be compared after the issue of Final Baseline Ecological Report. The ecological monitoring result in the Reporting Month is shown in Appendix L.

 

Complaint Log

13.  One environmental complaint for ND/2019/05 was received in the reporting month.

Notification of Summons and Successful Prosecutions

14.  No notification of summons or successful prosecutions was received in the reporting month.

Reporting Changes

 

15.  This report has been prepared in compliance with the reporting requirements for the subsequent monthly EM&A Report as required by the “Updated Environmental Monitoring and Audit Manual for Advance and First Stage Works of Kwu Tung North and Fanling North New Development Areas” (Updated EM&A Manual).

Future Key Issues

16.  The major site activities for the coming two months are shown in Table IV.


 

Table IV       Summary Table for Site Activities in the coming Two Months

Contract No.

Site Activities (January 2022 and February 2022)

ND/2019/01

 

(a)          Site Clearance, remove of existing structures and tree felling in Portion 1a

(b)         Site clearance, ground investigation, sheet piling, excavation and drainage in Portion 1b

(c)          Site Clearance and remove of existing structures in Portion 1e

(d)         Site clearance, tree felling and temporary road construction in Portion 2

(e)          Site clearance, backfilling, excavation and tree felling in Portion 3

(f)          Site clearance, sheet piling and excavation, drainage works and temporary road construction in Portion 5

(g)         Site Clearance, sheet piling and excavation, pipes laying, backfilling, construction of KB01 retaining wall, haul road construction in Portion 6a

(h)         Operation of HAC treatment facility in Portion 6b

(i)           Site clearance, sheetpiling and excavation, pipes laying and construction of APLR in Portion 7

(j)           Construction of retaining Wall, slope cutting, soil nailing, slope drainage and maintenance access construction, RC construction of flushing water service reservoir and fresh water reservoir, construction of temporary haul road in Portion 8a

(k)         Sheet piling for receiving pit, trenchless works, excavation in Portion 8b

(l)           Sheet piling and excavation, pipes laying, demolition of existing structures, GI works in Portion 9b

(m)       Stockpile of soil and excavation in Portion 9c

(n)         Excavation, sheetpiling for ELS, drainage works and road construction in Portion 10a

(o)         Sheetpiling and excavation, drainage works in Portion 10b

(p)         Construction of MBR at 11b

(q)         Construction of temporary sewage pumping station in Portion 14

ND/2019/02

(a)          Pre-bored Socketed H-pile

(b)         Tree felling

(c)          ELS

(d)         Hoarding erection

(e)          Pipe Jacking

(f)          Construction of Pile Cap

ND/2019/03

 

(a)        Portion 1 & Portion 1A

-            Drainage works at Yin Kong Road

(b)       Long Valley

-          Erection of Permanent Boundary Structure

-          Construction of Compacted Earth Bund / Walkway

-          Construction of Ditches

-          Construction of Irrigation Channel

-          Construction of Decking & Sluices

-          Construction of Type 1 Storage House

-          Construction of Type 2 Storage House

-          Construction of Tea House

-          Construction of Composting Facility

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Construction of Storage Sheds

-          Wetland Creation & Restoration works

ND/2019/04

 

(a)           Site clearance

(b)           Tree felling

(c)           Predrill

(d)           Bored piling

(e)           Excavation

(f)            Sheet piling

(g)           ELS

ND/2019/05

(a)           North Team Works

-          Pre-drilling for bored piles at B1 & B2(Portion II), C1(Portion II) & C1-03

-          Bored piling at B1(Portion I), B1&B2(Portion II), C1(Portion II), C1-03, C1-04, C2-01, C2-02, C2-03a, C2-03b, C3-02, C3-03a, C3-04a, D2-01, E2-01

-          ELS and Pile cap construction at C3-03b, C3-04b, C4-03, C4-04a, C4-04b, D1-01, D1-02, D1-03, D1-04, E1-01, E1-02, E1-03 & E1-04

-          Footing construction at C4-02.

-          Pier Construction at C4-03, C4-04a, C4-04b, D1-01, E1-01, E1-02, E1-03, E1-04

(b)          Viaduct Works

-          Installation of the 4th to 5th typical segment mould and SOP mould

-          Fabrication of 6th to 8th typical segment mould to be completed by the end of Feb 2022

-          1st and 2nd SOP

-          Target to cast in12 segments in and 16 segments

-          Fabrication of launching girder (LG) is in progress

-          Fabrication of 1st set Form Travel (FT)

-          Fabrication of pier bracket of Pier C4-04M

-          Complete ground beams of segment motorized trolley in CTC yard

(c)           South Team Works

-          Venton Area – Gas main laying, 11kv and 132kv cross road duct laying

-          Portion 13 –132kv duct laying. DN1200 storm drain construction

-          Portion 17 and 18 – Construction of DN 1650 storm. DN 600 and DN450 sewer

-          Portion 18 – 132kv duct laying, Gas main laying

-          Kee Kei area – demolish boundary wall

-          TWSR (West) – RW06 construction

-          HKY FB (East) – construction of LT1, P02

-          Portion 11 – DN1200 and DN600 watermain laying work

-          E2-02 pier – construction of tower crane foundation

-          E2-03 – Pile cap construction

-          E3-01 – Pile cap construction

-          E3-03 – Pier construction

-          D2-02 – Pile cap construction.

-          D2-03 – Temp. drainage diversion, access tower erection, temp. lighting, Piling works

ND/2019/06

 

(a)          Finishing works for the Management Office Building (MOB) at Portion 4.

(b)         Rectification works for T&C of E&M installations for the steel canopy, MOB and additional water tank and pump house at Portion 3

(c)          Construction of concrete carriageway at Portion 3

(d)         Construction of screeding on stall area at Portion 3

(e)          Construction of footings of additional covered walkway at Portion 3

(f)          Finishing works for the additional water tank and pump house at Portion 3

ND/2019/07

(a)        Site clearance at Portion 4 and 5

(b)        Erection of site hoarding at Portion 4

(c)        C&D waste disposal at Portion 1, 2, 4 and 5

(d)        G.I. works at Portion 4 and 5

(e)        Construction of box culvert at Portion 2

(f)         Filling works at Portion 1, 2 and 4

(g)        Tree felling/ Disposal of yard waste at Portion 4

(h)        Construction of site haul road at Portion 4

(i)         Demolition of villagers houses at Portion 4 and 5

(j)         Drainage works and sewage works at Portion 1, 3 and 4

(k)        Main piling works and Portion 5